Construction Projects Productivity in West African country of Benin: Case of Ground Earthworks
facebook(new window)  Pirnt(new window) E-mail(new window) Excel Download
 Title & Authors
Construction Projects Productivity in West African country of Benin: Case of Ground Earthworks
Akogbe, Romuald Kokou; Feng, Xin; Zhou, Jing;
  PDF(new window)
 Abstract
In this paper, a survey related to excavation construction activities among national and international construction companies was conducted to evaluate site productivity in construction industry. To analyze the respective productivity levels of each construction company, a benchmarking measures analysis that featured calculations of the performance ratio (PR) and performance management index (PMI) was performed. As a result of these analyses, it has been found that the work performed by local companies was marked by lower productivity and that of international companies was characterized by good productivity. Further analysis of construction workforce resources P% revealed that a construction company`s productivity is largely dependent on production capacity and consumption resources, which means that the retention of skilled workers and utilization of high-quality resources yields the highest level of productivity. These results suggest that for a local construction company to be competitive in the construction work market, it must retrain skilled craftspeople, foremen, engineers, and project managers, and strengthen its building capability by leveraging new equipment and technologies.
 Keywords
Construction productivity;labor productivity;construction companies;project management;construction project management;
 Language
English
 Cited by
 References
1.
Hanna A.S., Taylor C.S., Sullivan K.T., Impact of extended overtime on construction labor, Journal of Construction Engineering and Management JCEM, 131(6), 734-739, 2005 crossref(new window)

2.
Koskela L., Vrijhoef R., Is the current theory of construction a hindrance to innovation, Building Research & Information, 29(3) 197-207, 2001 crossref(new window)

3.
Willis C.J. and Rankin J.H., The construction industry macro maturity model (CIM3): theoretical underpinnings, International Journal of Productivity and Performance management, 61(4), 382-402, 2012 crossref(new window)

4.
Shouke C., Zhuobin W. and Jie L., Comprehensive evaluation for construction performance concurrent engineering environment, International Journal of Project Management, 28(7), 708-718, 2010 crossref(new window)

5.
Sahay B.S., Multi-factor productivity measurement model for service organization, International Journal of Productivity and Performance Management, 54(1), 7-22, 2005 crossref(new window)

6.
Stewart R. A. and Spencer C.A., Six-sigma as a strategy for process improvement on construction projects: a case study, Construction Management and Economics, 24(4), 339-348, 2006 crossref(new window)

7.
Hewage K.N. and Ruwanpura J.Y., Carpentry worker issues and efficiencies related to construction productivity in commercial construction projects in Alberta, Canadian Journal of Civil Engineering, 33(8), 1075-1089, 2006 crossref(new window)

8.
Zhai D., Goodrum P.M., Haas C.T., Caldas C.H., Relation between automation and integration of construction information systems and labor productivity, Journal of Construction Engineering and Management, 135 (8), 746-753, 2009 crossref(new window)

9.
Abdel-Razek R.H., AbdElshakour H.M., Abdel-Hamid M., Labor productivity: Benchmarking and variability in Egyptian projects, International Journal of Project Management, 25(2), 189-197, 2007 crossref(new window)

10.
Mojahed S., Aghazadeh F., Major factors influencing productivity of water and wastewater treatment plant construction: Evidence from the deep south USA, International Journal of Project Management, 26(2008) 195-202, 2008 crossref(new window)

11.
Tabassi A.A., Ramli M., Abu Bakar A.H., Effect of training and motivation practices on teamwork improvement and task efficiency: The case of construction firms, International Journal of Project Management, 30(2), 213-224, 2012 crossref(new window)

12.
Hwang S., Liu L. Y., 2010, Contemporaneous time series and forecasting methodologies for predicting short-term productivity, Journal of Construction Engineering and Management, 136 (9), 1047-1055, 2010 crossref(new window)

13.
Mojahed S., Aghazadeh F., Major factors influencing productivity of water and wastewater treatment plant construction: Evidence from the deep south USA, International Journal of Project Management, 26(2008) 195-202, 2008 crossref(new window)

14.
Ng S. T., Skitmore, R.M., Lam, C.K., Poon, A.W.C., Demotivating factors influencing the productivity of civil engineering projects, International Journal of Project Management,22(2), 139-146, 2004 crossref(new window)

15.
Nasirzadeh F., Nodejehi P., Dynamic modeling of labor productivity in construction projects, International Journal of Project Management, (2012), http:dx.doi.org/10.1016/j.ijproman.2012.11.003 crossref(new window)

16.
Khoramshahi F., Dehghan R., Mortaheb M.M., Factors influencing construction productivity. Proceedings of the 10th EASEC, 2006; p. 269-274. Bangkok. Thailand.

17.
Enshassi A., Mohamed S., Mustafa Z.A., Mayer P.E., Factors affecting labor productivity in building projects in the Gaza Strip, Journal of Civil Engineering and Management, 13(4) 245-254, 2007

18.
Alinaitwe H.M., Mwakali J.A., Hansson B., Factors affecting the productivity of building craftmen-studies of Uganda, Journal of Civil Engineering and Management, 13(3), 169-176, 2007

19.
Weng-Tat C., A systems perspective of construction productivity improvement efforts, Proceeding of the 1st International Conference of European Asian Civil Engineering Forum, Jakarta-Indonesia, p. E43-E50, 2007

20.
Hanna A. S., Chang C. K., Sullivan K. T., Lackney J. A., Impact of shift work on labor productivity for labor intensive contractor, Journal of Construction Engineering and Management, 134 (3) 197-204, 2008 crossref(new window)

21.
Kazaz A., Manisali E., Ulubeyli S., Effect of basic motivational factors on construction workforce productivity in Turkey, Journal of Civil Engineering and Management, 14(2), 95-106, 2008 crossref(new window)

22.
Dansoh, A. Strategic planning practice of construction firms in Ghana, Construction Management and Economics, 23(2), 163-168, 2005 crossref(new window)

23.
Ameh, O.J., & Odusami, K.T. Factors affecting labour productivity in Nigerian Construction Industry: A case study of indigenous contracting organizations in Lagos, The Quantity Surveyor, 40(3), 14-18, 2002

24.
Kaliba C, Muya M, and Mumba K. Cost escalation and schedule delays in road construction projects in Zambia, International Journal of Project Management, 27(5):522-531, 2009 crossref(new window)

25.
Mutijwaa P, and Rwelamila D. Project Management Competence in Public Sector Infrastructure Organisation, Construction Management and Economics, 25(1):55- 66, 2007 crossref(new window)

26.
Elattar S. M. S., Automation and Robotics in Construction: Opportunities and Challenges, Emirates Journal for Engineering Research, 13(2), 21-26, 2008

27.
Yang L. R., Impacts of automation technology on quality of project deliverables in the Taiwanese construction industry, Canadian Journal of Civil Engineering, 36(3), 402-421, 2009 crossref(new window)

28.
Corke P., Winstanley G., Dunlin M., Robert J., Dragline Automation: Experimental Evaluation through Productivity Trial, In: Advances inTele-Robotics, Siciliano, B; Khatib, O. & Groen, F. (Ed.), pp. 459-468, Springer, 2006; ISBN: 78-3-540-32801-8, Berlin.