VRIO Model Based Enterprise Capability Assessment Framework for Plant Project
facebook(new window)  Pirnt(new window) E-mail(new window) Excel Download
 Title & Authors
VRIO Model Based Enterprise Capability Assessment Framework for Plant Project
Min, Byeong Su; Min, Jang Hee; Jang, Woosik; Han, Seung-Heon; Kang, Sin Young;
  PDF(new window)
 Abstract
Construction enterprises have performed various projects such as buildings, infrastructure and plant projects in the international market. Among these, the plant project`s amount of orders accounted for about 68.9% of all. However, because of the enterprises won a contract with a low-budget for plant project in the last 10 years, the profit has dropped dramatically. And it is forecasted that there are extreme competition for bid award of plant projects because of the current falling oil prices and raising interest rates. In this circumstance, the comprehending of enterprises strength and weakness must be a priority to get a sustainable competitive advantage. Therefore this research suggests the enterprises`s capability assessment framework and it is in order to diagnose the korean construction enterprises capabilities. The framework is based on the VRIO model that is on the basis of resource based theory. First, the capability assessment indices and their importance and priority that based on the life-cycle of plant project is deducted by literature review and survey. Second, the 5 point likert score applied VRIO survey is conducted to diagnose the enterprises and quantified the survey result using the fuzzy theory. Lastly, the competitvie implication and capability assessment are deducted.
 Keywords
Resource Based Theory;VRIO Model;Plant Project;Capability Assessment;
 Language
Korean
 Cited by
 References
1.
Alavi, Maryam, and Leidner, D. E. (2001). "Review: Knowledge management and knowledge management systems: Conceptual foundations and research issues." MIS quarterly, pp. 107-136. crossref(new window)

2.
Bae, S. Y. (2010). "Deduction of the Component Factor for International LNG Plant Project Feasibility and Analysis of the Priority" Chung-Ang Univ.

3.
Chan, A. PC., and Chan, A. PL. (2004). "Key performance indicators for measuring construction success." Benchmarking: an international journal, 11(2), pp. 203-221. crossref(new window)

4.
Choi, S. B. and Ha, G. R. (2011). "A Study of Critical Factors for Technological Innovation of Korean Manufacturing Firms", Korean Industrial Economic Association, 24(1), pp. 1-24.

5.
Chung, S. B., Choi, J. H., Shin, Y. S. and Chang K. T. (2013). "Evaluation Criteria of Competitiveness and Their Weighted Values for Railway Supply Industry" Journal of the Korean Society for Railway, pp. 1265-1268.

6.
Han, J. G., Chin, K. H. and Park, H. P. (2010). "Elicitation Project Management Factors and Evaluation of its Weight to Ensure LNG Plant Success" The Korea Institute of Building Construction, 10(1), pp. 85-89.

7.
International Construction Association of Korea(ICAK). (2015). International Construction Information Service. (Jan. 4, 2016)

8.
Jang, W. S., Hong, H. U. and Han, S. H. (2011). "Risk Identification and Priority method for Overseas LNG Plant Projects - Focusing on Design Phase" Korean Journal of Construction Engineering and Management, , KICEM, 12(5), pp. 147-154.

9.
Kang, S. H. , Lee, H. J. and Leem C. S. (2010). "Analys is of Individual Capability Factors to Improve Business Performance in the Environment of Technological Convergence." Society for e-Business Studies, 15(3), pp. 183-193.

10.
Kang, H. W., (2012). "A Study on the Analysis of Risk Factors in Engineering, Procurement and Construction Phase for Overseas Plant Project" Journal Of The Architerctural Instritute of Korea Structure and Construction, 28(5),pp. 111-118.

11.
Kim, J. M., (2011). "Analysis of the Construction Duration and Cost Variation of International LNG Plant Project on EPC Risk factors" Chung-Ang Univ.

12.
Kim, J. U., Kim, J. B., Kim, T. U. and Park, S. T. (2013). "A case study on digital signage in korea." The journal of Digital Policy, pp. 149-158.

13.
Kim, K. S. and Lee, K. H. (2014). "The Impact of Resources on Organizarional performance in Public Research Institutes : From the Resource-Based View" The Korea Institute of Public Administration, 23(2), pp. 113-142.

14.
Kometa, Simon, T., PAUL, Olomolaiye, O., and Harris, F. C. (1995). "An evaluation of clients' needs and responsibilities in the construction process." Engineering, construction and Architectural management, 2(1), pp. 57-76. crossref(new window)

15.
Kumaraswamy, M. M., and Thorpe, A. (1996). "Systematizing construction project evaluations." Journal of Management in Engineering, 12(1), pp. 34-39.

16.
Langdon, D. and Marrelli, A. (2002). "A New Model for Systematic Competency Identification," Performance Improvement, 41(4), pp. 16-23.

17.
Lee, C. W. (2001). "Country Competitiveness Theory of Michael E. Porter" Korea Research Institute for Human Settlement, pp. 60-65.

18.
Lim, C. S. and Mohamed, M. Z. (1999). "Criteria of project success: an exploratory re-examination" International journal of project management, 17(4), pp. 243-248. crossref(new window)

19.
Lim, J. A. and Kwon, S. W. (2011). "Analysis of success factors in construction IT convergence: applying AHP." Korean Journal of Construction Engineering and Management, KICEM, 12(4), pp. 130-138.

20.
Marrelli, A. (1998). "An introduction to competency analysis and modeling" Performance Improvement, 37(5), pp. 8-16.

21.
Michael, G. (2014). "Success Factors of Plant Engineering Project" Procedia Engineering, 69, pp. 361-369. crossref(new window)

22.
Mirabile, R. (1997). "Everything You Wanted to Know about Competency Modeling." Training and Development, 51, pp. 73-77.

23.
Noh, K. J. (2015). "Intensified lease hardship hit the international win a contract... Construction companies suffer a direct hit" (Jan. 15, 2016)

24.
Park, C. J. (2004). "A Fuzzy Model for the Competitiveness Evaluation and Performance Measurement of Business." Management Accounting Association of Korea, 4(2), pp. 61-83.

25.
Park, H. P., Han, J. G. and Chin, K. H. (2010). "Development the Decision Making Support System of Construction Management in LNG Plant Project." The Society of Air-Conditioning and Refrigerating Engineers of Korea, pp. 818-823.

26.
Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M., and Coyle, M. (1992). "Critical success factors for construction projects." Journal of construction engineering and management, 118(1), pp. 94-111. crossref(new window)

27.
Shrnhur, Aurmi J., Levy, O. and Dvir, D. (1997). "Mapping the dimensions of project success." Project management journal, 28(2), pp. 5-13.

28.
Son, J. H., Lee, S. Y., Han, C. H. and Kim, J. o. (2007). "A Study on the Critical Success Factors for Engineering step on Plant Project" Korean Journal of Construction Engineering and Management, KICEM, 8(6), pp. 227-234.

29.
Spender, J. C. and Grant, R. M. (1996). "Knowledge and the firm: overview." Strategic management journal, 17.S2, pp. 5-9. crossref(new window)

30.
Tak, H. W., Won, S. K., Hwang, K. H., Han, C. H. and Lee, J. B. (2010). "Development on Standard Process of Pre-Construction Phase for Overseas Plant Projects" The Society of Air-Conditioning and Refrigerating Engineers of Korea, pp. 806-811.

31.
Won, S. K., Kang, M. W., Lee, J. B., Kim, S. K. and Han C. H. (2008). "An Analysis of Procurement Processes for the Application of System Prototype of Overseas Plant Projects" Journal of the Architectural Institute of Korea Structure & Construction, 24(2), pp. 113-120.

32.
Yang, S. W. and Jung, J. S. (2015). "The Case Study on Elon Musk and Tesla Motors: Based on the Analyses of Competitive Advantage Using Diamond Model" Management Consulting Research, 15(2), pp. 197-209.