Application of Reliability Centered Maintenance Strategy to Safety Injection System for APR1400
facebook(new window)  Pirnt(new window) E-mail(new window) Excel Download
 Title & Authors
Application of Reliability Centered Maintenance Strategy to Safety Injection System for APR1400
Rezk, Osama; Jung, JaeCheon; Lee, YongKwan;
  PDF(new window)
 Abstract
Reliability Centered Maintenance (RCM) introduces a systematic method and decision logic tree for utilizing previous operating experience focused on reliability and optimization of maintenance activities. In this paper RCM methodology is applied on safety injection system for APR-1400. Functional Failure Mode Effects and Criticality Analysis (FME&CA) are applied to evaluate the failure modes and the effect on the component, system and plant. Logic Tree Analysis (LTA) is used to determine the optimum maintenance tasks. The results show that increasing the condition based maintenance will reduce component failure and improve reliability and availability of the system. Also the extension of the surveillance test interval of Safety Injection Pumps (SIPs) would lead to an improved pump`s availability, eliminate the unnecessary maintenance tasks and this will optimize maintenance activities.
 Keywords
Reliability Centered Maintenance;Safety Injection System;APR-1400;
 Language
English
 Cited by
 References
1.
IAEA-TECDOC-1590 Application of Reliability Centered Maintenance to Optimize Operation and Maintenance in Nuclear Power Plants, May 2007.

2.
Rausand M, Reliability centered maintenance Reliability Engineering and system Safety vol.60, pp2, 1998.

3.
APR1400 Safety Analysis Report, (2004).

4.
KHNP, "APR1400 Technical Specification", (2010).

5.
Alexander Kossiakoff, Systems Engineering Principles and practice 2nd Edition, John Willey& Sons Publishers, 57-159, 2011.

6.
INPO, Equipment Reliability Process Description, INPO AP-913, Rev. 3, 2011.

7.
EPRI, Preventive Maintenance Basis Database (PMBD), Ver. 5.1.1, 2004.

8.
EPRI, Critical Component Identification Process-Licensee Examples, TR-1007935, 2003.

9.
The basic concepts of failure analysis, Marvin Rausand & Knut Oien, Reliability Engineering and System Safety 53, January 1996.

10.
Kim, Y. "Risk Informed Allowed Outage Time Change for Units 3&4" (2001).

11.
KAERI/TR-1772, "Risk-Informed Allowed Outage Time Change for Ulchin Units 3&4", 2001.

12.
Systems engineering approach to Reliability Centered Maintenance of Containment Spray Pump, Ohaga Eric Owino & Jung Jae Cheon, and Lee Yong-Kwan. Journal of the Korea Society of Systems Engineering vol.9, June 2013.