Formal Estimation Method for Optimal Budget Appropriation of Highway Construction Projects under Long-term Continuation Contracts
facebook(new window)  Pirnt(new window) E-mail(new window) Excel Download
 Title & Authors
Formal Estimation Method for Optimal Budget Appropriation of Highway Construction Projects under Long-term Continuation Contracts
Koo, Bon-Sang; Yu, Jung-Ho; Park, Jong-Ho;
  PDF(new window)
 Abstract
In Korea, public infrastructure projects employ "long term continuation (LTC) contracts," which require budgets to be reevaluated and re-appropriated annually throughout the multi-year life of the project. However, such contracts also make it susceptible to frequently changing government policies, in which budgets required for existing projects are allocated to new projects and thus does not provide a consistent stream of capital to multi-year projects. Each year, the KEC needs to attain government funds for construction of its multiple highway construction sites. Because it is difficult to know the amount that may be actually appropriated to KEC in a given year, it is in turn difficult to anticipate and provide sufficient funds necessary for construction to run smoothly and continuously. The lack of a good logic for appropriation has resulted in projects having a skewed distribution of capital. To get better budget appropriations from the central government, the KEC first needs a systemized approach that rationalizes the annual construction capital optimally required for its individual sites. The goal of this research was to devise a way that allows the KEC to determine and calculate the optimal construction costs that would be required for its individual construction sites on an annual basis. Both the optimal progress rate and the essential work types were assessed through a workshop with 24 professionals (KEC employees and contractors) who had extensive experience in KEC projects and also were currently working in these projects.
 Keywords
Optimal construction cost;Highway construction;Long term continuation contracts;
 Language
Korean
 Cited by
 References
1.
Jung, W. and Kim, D. I. (2013). "Constitutional status and improvement of consistent long-term construction contracts continue." Attormeys at Law Yulchon, Ministry of Strategy and Finance.

2.
Jung, Y. C. (2013). "Construction of air extending the main dispute cases and problems." Global Construction Leaders, Korea federation of Construction Contractors. No. 12. pp. 08-12.

3.
Kim, S. B., Lee, J. D. and Jo, J. H. (2008). "An empirical study on the effect of public construction industry by expansion of new budget system." Korean Journal of Construction Engineering and Management, Vol. 9, No. 3, pp. 153-163.

4.
Lee, S. H. (1996). "Problems and solutions for continued long-term contract system." Construction Industry Trends, Construction & Economy Research Institute of Korea, Vol. 7, No. 1, pp. 1-11.

5.
Lee, S. H. (1999). "Budget processes and long-term continuation of a multi-year contract drafting business." The Korea Association for Policy Studies, Vol. 8, No. 1, pp. 231-248.

6.
Lee, Y. S. (2011). "Development of innovative construction cost engineering system for public construction projects in Korea." Land transport and maritime R&D report.

7.
Ministry of Land, Infrastructure and Transport (2013). "Road Services Manual." (in Korean).

8.
Ministry of Strategy and Finance (2010). "In 2010 state contract system Advancement Plan." (in Korean).

9.
Ministry of Strategy and Finance (2012). "Total business expense management guidelines." (in Korean).

10.
Ministry of Strategy and Finance (2013). "Detailed Instructions of Budget Making." (in Korean).

11.
Ok, D. S. (1995). "Selection and budgeting for large government projects." Korea Development Institute.

12.
Park, H. K., Shin, K. C., Park, H. P. and Jung, Y. S. (2008). "A study of the future strategy and mission for the stakeholders in industry, Academy, and Government for the revitalization of CM." Korean Journal of Construction Engineering and Management, Vol. 9, No. 6, pp. 244-256.

13.
Park, J. W. (1998). "Science and technology to improve organization and execution of research and development budget system." Presidential Advisory Council on Science & Technology.

14.
Ryu, C. S., Jang, S. H., Kim, K. R. and Lim, K. I. (2002). "Concept and standard of fair construction cost in the domestic construction industry." Journal of the Architectural Institute of Korea Structure & Construction, Vol. 18, No. 3. pp. 157-164.

15.
Yoon, K. Y., Whang, S. H. and Park, J. W. (2001). "2002 budget needs analysis." Assembly Budget Committee.