Optimization of Multiple Tower Cranes and Material Stockyards Layout

다중 양중장비와 자재 야적 위치의 최적 결정을 위한 모델 개발

  • 김경주 (중앙대학교 건설환경공학과) ;
  • 김경민 (중앙대학교 토목공학과) ;
  • 이상규 (중앙대학교 토목공학과)
  • Published : 2009.11.30

Abstract

This study aims to provide an optimal model for the layout of multiple tower cranes and material stockyards which have multiple candidate positions. In a high-rise building construction, the positional allocation of tower cranes and material stockyard has an effect on the travel time of material hauling. In addition, in case of using multiple tower cranes, specific location of a tower crane allocated to each material determines the efficiency of the works. Current optimal model limited to the optimization of position of single tower crane and material stockyards. This study suggests optimal model both for the positions of multiple tower cranes and material stockyards. Layout of multiple tower cranes requires additional allocation of each crane to each material hauling and control on the minimum distance between tower cranes. This optimization model utilizes genetic algorithm to deal with complex interaction on the candidate positions of multiple tower cranes, material stockyards, and types of materials. In order to identify its utility, case study was performed.

References

  1. 김정진 (2002), 초고층 건축공사의 양중계획 시스템에 관한 연구, 명지대학교 박사학위논문
  2. 최인성 (1985), 초고층 건축의 양중계획에 관한 연구, 중앙대학교 박사학위논문
  3. Choi, C. W., and Harris, F. C. (1991). 'A model for determining optimum crane position.' Proceedings, Institution of Civil Engineers, 90(June), pp. 627-634 https://doi.org/10.1680/iicep.1991.14735
  4. Gray, C., and Little, J. (1985). 'A systematic approach to the selection of an appropriate crane for a construction site.' Construction Management and Economics, 3, pp. 121-144 https://doi.org/10.1080/01446198500000010
  5. Jenkins, W. M. (1997). 'On the application of natural algorithm to structural design optimization.' Engineering Structures, 19(4), pp. 302-308 https://doi.org/10.1016/S0141-0296(96)00074-0
  6. Koumousis, V. K., and Georgiou, P. G. (1994). 'Genetic algorithms in discrete optimization of steel truss roofs.' Journal of Computing in Civil Engineering, ASCE, 8(3), pp. 309-325 https://doi.org/10.1061/(ASCE)0887-3801(1994)8:3(309)
  7. Leu, S. S., and Yang, C. H. (1999). 'A genetic-algorithmbased resource constrained construction scheduling system.' Construction Management and Economics, 17(6), pp. 767-776 https://doi.org/10.1080/014461999371105
  8. Li, H., and Love, P. E. D. (1988). 'Site-level facilities layout using genetic algorithms.' Journal of Computing in Civil Engineering, ASCE, 12(4), pp. 227-231 https://doi.org/10.1061/(ASCE)0887-3801(1998)12:4(227)
  9. Rodriguez-Ramos, W. E., and Francis, R. L. (1983). 'Single crane location optimization.' Journal of Construction Engineering and Management, ASCE, 109(4), pp. 387-397 https://doi.org/10.1061/(ASCE)0733-9364(1983)109:4(387)
  10. Tam, B. M., Tong, Thomas K. L., and Chan, Wilson K.W. (2001) 'Genetic Algorithm for Optimizing Supply Locations around Tower Crane.' Journal of Construction Engineering and Management, ASCE, 127(4), pp. 315-321 https://doi.org/10.1061/(ASCE)0733-9364(2001)127:4(315)
  11. Zhang et al. (1999). 'Location Optimization for a Group of Tower Cranes.' Journal of Construction Engineering and Management, ASCE, 125(2), pp. 115-122 https://doi.org/10.1061/(ASCE)0733-9364(1999)125:2(115)