A Study on Periodic Buffer Allocation for Program Master Schedule

프로그램 공정계획을 위한 주기적 버퍼 설치에 관한 고찰

  • Published : 2001.11.01

Abstract

In a dynamically changing environment, the manager of a maintenance and remodeling (M/R) program is confronted with an increasing complexity of coordinating and cooperating multi-resource constrained multiple projects. The root causes of the complexity, uncertainty and interdependence, cause an internal disruption of an activity and chain reactions of disturbance propagation that deteriorate the stability and manageability of the program. This paper evaluates previous endeavors to apply production control and management techniques to the construction industry, and investigates the possibility of applying other management concepts and theories to organizational program management. In particular, this paper proposes a buffer allocation model by which periodic buffers are allocated in the flows of program constraint resources to stabilize a program master schedule instead of protecting individual activities. Comparative experiments by Monte Carlo simulations illustrate improved performance of the proposed model in terms of program's goals: productivity, flexibility, and long-term stability.

동적 변화가 상존하는 건설환경에서, 보수·리모델링 프로그램의 관리자는 자원하의 복수 프로젝트를 조정·관리하는데 어려움을 겪게 된다. 프로그램에 내재하는 불확실성과 상호종속성으로 인해, 단위작업의 지연과 그로 인한 연쇄적인 공정계획의 동요는 프로그램 전체의 안정성과 관리가능성을 저해한다. 본 논문은 먼저 건설관리에 적용되었던 생산관리기법들이 프로그램관리에 적용될 수 있는가를 살펴본 후, 프로그램 내부의 자원유동의 흐름에 주기적으로 버퍼를 설치하는 공정 안정화 모델을 제안하고자 한다. 몬테-칼로 시뮬레이션에 의한 비교실험으로 제안된 버퍼 관리모델의 성능을 프로그램의 생산성, 유연성, 그리고 안정성의 관점에서 분석하였다.

Keywords