To examine the construction plan of the lightening rod equipment for the intake tower of D-dam

D댐의 취수탑 피뢰설비 구축방안 검토

  • Published : 2003.07.21

Abstract

The intake tower of D-dam located in a mountainous area positioned in the left side of the dam and its structure installed alone on the water surface then, can become target of direct lightening. To protect the intake tower from the direct lightening and indirect-lightening, lightening rod installed in the top area of the intake tower and ground pole laid under the surrounding ground. however, because the surrounding ground almost consists of a rock, it is very difficult to obtain the grounding resistance. It is main object to examine the construction plan of the optimum lightening rod equipment and ground pole with measuring the earth specific resistance of the around of the intake tower which is the scheduled area to lay the ground pole with the Wenner's 4-electric pole method and the Schlumberger's method. and using the analysis tool, ESII.

Keywords