A Delay Analysis based on the Comparison of the As-planned Schedule, As-built Schedule including All Delays and As-built Schedule absent Owner Delays

계획공정표, 모든 지연을 포함한 준공공정표, 발주자 지연을 제외한 준공공정표의 비교를 통한 공기지연분석

  • Published : 2003.11.01

Abstract

In the construction process, there are many change orders differing to the initial contracts came from the social needs and environmental changes. Most of them will impact to the construction process so that its effects occur project delays. Time extension and liquidated damage in the construction process come from schedule delay whether it is excusable or not non-excusable by the owner. However, those become the delay claims if the owner and the contractor are not agreed on this situation. One of the most important thing on the delay claims is the calculation of delay. The purpose of this study is to present the method of the time delay calculation by comparison of As-Planned schedule, As-Built schedule including all delay and As-Built schedule absent owner delay.

건설공사는 프로젝트의 진행 중 내${\cdot}$외부의 여러 조건의 변경이나 사회적 요구에 따라 초기의 계약과는 다른 많은 변경사항이 발생하게 된다. 이러한 변경사항은 프로젝트 추진과정에서 많은 영향을 미치게 되며, 이로 인하여 발생되는 영향은 대부분 프로젝트의 공기지연으로 나타나게 된다. 건설공사에서 발생하는 공기 지연은 기본적으로 도급자의 면책여부에 따라 공기연장이나 지체상금의 부과 등의 결과로 나타나게 되는데 이러한 사항에 대한 발주자와 도급자의 의견이 대립될 경우 클레임으로 발전하게 된다. 클레임에서 가장 중요한 사항은 공기지연일수의 산정으로서 이는 공기지연 클레임에서 가장 중요한 부분이라고 할 수 있다. 본 연구에서는 공기지연 클레임에서 가장 중요한 자료가 되는 공기지연일수 산정방법의 한 방법으로 계약 초기에 작성된 계획공정표(As-Planned Schedule)와 모든 지연이 포함된 준공공정표(As-Built Schedule including all delays) 그리고 발주자 지연이 제외된 준공공정표(As-Built schedule absent owner delays)를 비교함으로써 각 계약 구성원의 귀책으로 인한 광기 지연일수 산정방법을 제시하고자 한다.

Keywords