A method of Calculating Optimal Duration and Cost Using Monte Carlo Simulation and Linear Programming

몬테카를로 시뮬레이션과 선형계획법을 이용한 최적의 일정 및 비용 산정방법

  • 김용득 (부경대학교 대학원 토목공학과) ;
  • 이영대 (부경대학교 건설공학부)
  • Published : 2004.11.01

Abstract

In can occur to many problems on progressing step without close scope definition, interrelation definition between activities, resource plan, and schedule plan on planning step. But it have not closely defined performance system on planning step because of many constraints of domestic construction industry. Therefore this paper intends to discuss a method of calculating optimal cost and duration using Linear Programming that solves maximing or minimizing problems among decision making methodology and Monte Carlo Simulation that decreases to probability errors. With outcoms applying Linear programming and Monte Carlo Simulation for calculating optimal cost and duration, follow as : With outcomes applying Monte Carlo Simulation, it could calculate reliable estimator about project duration through removing various constraints. With outcomes applying Linear programming, it could calculate optimal value about project cost through defining various variables and constraints on many activities.

프로젝트의 계획단계에서 명확한 업무의 정의와 업무간의 상관관계, 자원계획 및 일정계획이 수행되지 않으면, 공사의 진행 시에 많은 변경과 일정 $\cdot$ 비용 상의 문제를 가져올 수 있다. 그래서 본 연구에서는 사례연구를 중심으로 프로젝트 계획단계에서 최적의 소요공기 산정을 위해서 몬테카를로 시뮬레이션과 선형계획법을 적용한 결과, 다음과 같은 결론을 얻었다. 몬테카를로 시뮬레이션을 사용함으로써 각각의 활동이 독립적이고, 프로젝트 소요시간에 대해서 정규분포를 따른다는 가정의 제약조건을 해소함으로 보다 신뢰한 만한 일정 추정이 가능하였으며, 주 경로와 주 경로에 근접한 경로에 신뢰할 만한 일정편차를 계산할 수 있었다. 또한, 선형계획법을 동해서 최적의 소요비용 산정이 가능하였으며, 프로젝트 목표소요공기의 변동에 따른 최적의 목표공기를 산정할 수 있었다.

Keywords