Optimal Project Duration Estimation Through Enhanced Resource Leveling Technique

개선된 자원 평준화 기법을 활용한 적정 공기산정에 관한 연구


Abstract

Since a construction project is a series of works that utilizes resources to accomplish the project goal for a given time period, efficient resource management is a prerequisite for the success of the project. Two major areas of resource management are resource constrained scheduling focusing on the limited resource availability and resource leveling focusing on smoothing resource usage pattern on the fixed project completion time. It is not available, however, to apply both techniques to a project at the same time. This paper proposes a model to enhance the minimum moment algorithm of resource leveling, aiming to find an efficient usage of resources and an appropriate project completion time. A survey is performed to evaluate the major five factors using the AHP.

건설프로젝트는 일정한 기간 동안 주어진 목표를 수행하기 위한 작업들의 모임이라 정의할 수 있으며, 이를 위해서는 필요한 자원의 효율적 계획 및 관리가 필요하고, 이때 자원배당 및 자원평준화 기법이 활용된다. 하지만 자원제약이 있는 자원배당과 공기 제한이 있는 자원평준화 방법은 하나의 프로젝트에 개별적으로 적용되고 있어 전체 프로젝트의 공기와 효율적 자원이용 측면에서 적정화하기는 어렵다. 따라서 본 연구는 자원 평준화 방법의 Minimum Moment Algorithm 개념을 확대 $\cdot$ 적용하여 적정 자원이용 및 공사기간을 산출하고자 한다. 이때 자원 활용의 상태를 나타내는 5가지 지표들 사이의 중요도는 AHP기법을 통해 파악한다.

Keywords