수해복구 현장 시공사례(영동선 분천${\~}$승부간 각금천 제1, 2교량)

A Case study on a flood disaster restoration work

  • 신현곤 (극동건설주식회사 토목기술영업팀) ;
  • 김지훈 (극동건설주식회사 영동선 각금천 건설현장) ;
  • 배준현 (극동건설주식회사 토목기술영업팀) ;
  • 이주혁 (극동건설주식회사 토목기술영업팀)
  • 발행 : 2004.06.01

초록

Recently the unexpected damage is broken out by the unusal change of weather. Misfortune on top of misfortune the typhoon did great damage again before finishing the repair work. And then we should study about the repair work of fast and safety as well as the construction of safety. The paper suggests the case study of a fast disaster restoration work. To minimise the term of repair work which selects Fast Track Method. This work is processed as follows. Temporary resortation is progressed at the same time as the main resortation. And In this paper, technique to evaluate the capacity of bridge is tried to develop by means of FEM analysis.