The Analysis of 2004 Summer Peak Load in Korea Power system

2004년 하계 첨두부하 시 계통운영 실적 분석

  • Published : 2004.11.12

Abstract

This year korea power system had recorded highest peak load for 6 times and finally it made new peak load 51,264MW at July 29th 3:00 PM. The new peak load is increased 8.2% from the last year peak load 47,385MW and korea power system entered 50,000MW load era. The Korea Power Exchange (KPX) snapped power system data at the peak load time using state estimation function in the EMS. And authors converted the power system data at peak load to PSS/E power flow format. Using this PSS/E peak load power flow data, this paper explains demand analysis result shun capacitor operation, voltage distribution at the peak load. And the paper shows the simulation result of 2 contingency analysis using the snapped PSS/E peak load data.

Keywords