초록

345kV youngheung tansmission line which has been constructed in the western sea is the first and the largest marine project in the world crossing the youngheung island and the sihwa bay. It helps the stabilization of power supply greatly to cope with the rapid growth of the electric power consumption in the metropolitan areas and Gyeonggi province. Haying constructed the project successfully with the purely domestic-developed technologies, KEPCO is able to not only accumulate more advanced technologies of the marine project but also establish a bridgehead toward overseas market. It is very meaningful that we completed project successfully in spite of many difficulties including the uncertainty of the first project in the sea and strong objections from the environment groups and local residents. In this paper I will briefly introduce the project, newly developed technologies and materials.