Review about test method for the full-insulation verification of circuit breaker rated on 800kV, 50kA

800kV, 50kA 차단기의 전절연 검증을 위한 시험방법 검토

  • Published : 2005.07.18

Abstract

In case of dead-tank circuit breaker with the earthed enclosure, the dielectric performance for phase to ground should be verified under the hot-gas condition produced by the current interruption. This test condition is required in breaking test duties with the rated short-circuit current and rated voltage. And, KERI has completed the reinforcement of the synthetic testing facilities and these facilities have the testing capacity which enables the full-pole testing for 800kV circuit breaker by adopting the series voltage injection method. So, this paper introduced the test circuit and procedures about the full-pole and the multi-part testing method which was devised to estimate the full -insulation of phase-to-ground for the multi-pole and dead-tank circuit breaker.

Keywords