Measurement during Construction of Nakdong Bridge by Incremental Launching Method

낙동강교 ILM 가설에 따른 시공 중 계측

  • Published : 2007.11.08

Abstract

As the volume of traffic in southern part of the republic of Korea grew, expansion of transportation was required. In that purpose, the railway between Samnangjin and Gwangyang is being extended to a double-track line. This construction includes Nakdong bridge located across Nakdong river. This truss bridge is constructed in incremental launching method (ILM) and composed of two sections, straight line and curved one. Bridge construction in the method goes with the shift of roller supports which results in the change of structural system. To accomplish safe construction, the measurement during the whole launching stages. The locations of member in severe condition and the corresponding response values were estimated through the preliminary construction stage analysis. Based on the analysis, the measurement during construction was planned. Several sensors and measurement devices were installed at appropriate locations. During the whole launching stages, the measurement was performed and the corresponding data were monitored and stored in real time. The comparison of the responses from the analysis and the measurement showed no indication of yielding of the structural members. Consequently, the construction of Nakdong bridge was concluded to be relevant.

Keywords