Identification of Factors Affecting Time and Cost Performance in Vietnam Construction Projects

  • Published : 2007.11.09

Abstract

In-planned duration and cost at project closing are the two of criteria of successful project and successful project management. In Vietnam, regularly, construction projects are delayed and their costs are overrun. This research employed a questionnaire survey to elicit the causes of this situation by interviewing 87 Vietnamese construction experts. After processing data, 21 causes of delay and cost overruns appropriate with building and industrial project in construction stage were inferred and ranked. Spearman's rank correlation tests showed that there're no differences in the viewpoints between parties in project.