A Productivity Analysis Method of Curtain Wall Works Using Construction Simulation

건설 시뮬레이션을 활용한 커튼월 적층공법의 생산성 분석방안

  • 박동근 (인하대학교 건축공학과) ;
  • 이경석 (인하대학교 건축공학과) ;
  • 유병인 (인하대학교 건축공학과) ;
  • 김영석 (인하대학교 건축공학과) ;
  • 한승우 (인하대학교 건축공학과)
  • Published : 2008.11.07

Abstract

The curtain-wall work has been more frequently applied in the construction industry since demand of high-rise buildings has been increased. The curtain-wall work is usually performed with the frame work simultaneously for reducing construction period, but it might be delayed because of several problems caused by interference of process. However, there is not an appropriate tool which can be used by a work manager for adjusting quantity of the construction equipments or the workers when the curtain-wall work was delayed. To resolve this problem a construction simulation anticipating and analyzing potential problems before starting the work can be applied in the curtain wall work. This research suggests a general model for the curtain-wall work by using construction simulation and produces a combination of construction equipments and workers which can estimate optimum work productivity.

최근 사회 경제적 요구의 증가, 건설기술 및 공법의 발전, 고객의 다양화 등 건설 환경의 급격한 변화로 인해 고층건물이 과거에 비해 크게 증가하고 있으며, 고층화 및 고급화 경향에 따라 고층 오피스공사의 외부마감으로만 사용되던 커튼월공사가 고층 아파트 및 주상복합의 외부마감으로 확대 사용되고 있다. 전체 공사비의 $10{\sim}15%$를 차지하는 주요공정인 커튼월 공사는 최근 공기단축을 목적으로 골조공사가 시작한 일정시점 이후부터 커튼월 공사를 동시에 시작하는 방식인 적층공법이 많이 사용되고 있다. 하지만 커튼월 적층공법은 두 작업이 동시에 진행됨으로써 발생되는 작업간 간섭에 의해 커튼월 공사의 공기가 지연이 되는 문제점이 있는데, 노무자 투입에 관한 방법론과 전산화 시스템의 부재로 인해 효율적인 해결책이 제시되지 못하고 있는 실정이다. 이를 위한 방안으로 가상공간에서 실제공사를 수행하기 전 미리 문제점을 예측하고 분석할 수 있는 건설 시뮬레이션 기법이 있지만 아직 건축공사에는 그 적용이 전무한 실정으로 이 논문에서는 대표적인 건설 시뮬레이션 기법인 사이클론을 이용하여 커튼월 적층공법의 작업 프로세스 일반화 모델을 개발하여 노무 및 장비 자원의 투입량에 따른 작업 생산성을 예측하였다. 이 연구의 결과는 현장관리자의 노무 및 장비 투입을 위한 효과적인 의사결정 도구로 활용될 수 있으며, 공기지연 시 원인분석 도구로 활용될 수 있을 것으로 기대된다.

Keywords