The Installation of Turnout on High Speed Operating Line

고속철도 운행선구간에서의 분기기 설치 기법

  • 최유복 (한국철도시설공단, 고속철도 궤도처) ;
  • 김인재 (한국철도시설공단, 고속철도 궤도처) ;
  • 하복수 (한국철도시설공단, 고속철도 궤도처 궤도1팀) ;
  • 신순호 ((주)케이알티씨, 궤도사업본부)
  • Published : 2010.06.10

Abstract

To install turnout on the main line of high speed railway running 300km/h, measures of rail destressing of existing line, speed-up plan, shortening the installation time and other important technical measures should be considered to reduce the inconvenience of passenger. In particular, for the newly constructing Ohsong and Kimcheon-Gumi station in KyongBu high speed line, it must be difficult to install divided turnout part because it should be done within short night block out hours (6 hours per day) and KTX trains are safely serviced just in time, which is not only the first time in the domestic and but also very rare practical experience in the world. This thesis is covered with experienced work conditions, required equipments and various safety measures, etc.

300km/h의 고속으로 운행중인 선로구간에 중간역 설치에 따라 분기기 부설시 기존선로의 레일응력 해소방안이 필요하며 또한 속도제한을 높게 하고 기간을 단축시킬 수 있는 방안을 통해 열차 이용객의 불편을 최소화하여야 한다. 경부고속철도 중간역사 오송, 김천구미역 신설에 따른 분기기 설치는 짧은 야간 차단작업시간(1일 6시간)에 여러 부분으로 나누어 시행하여야 하고 곧바로 고속열차를 운행시켜야 하는 매우 어려운 조건으로서 국내에서는 처음이고 세계적으로도 매우 드문 사례이다. 본 논문에서는 작업조건, 장비, 안전조치 등에 관한 사항을 제시하였다.

Keywords