A Study on the Storage-Yield Relationship of Reseroir

저수지의 Storage-Yield에 관한 연구

  • Published : 1985.09.01

Abstract

Basically, there are two ways viewing the reservoir storage-yield relationship., The most common viewpoint is the determination of the storage required at a given reservoir to supply a required yield. This type of problem is usually encountered in the planning and early design phases of a reservoir. The second viewpoint is the determination of yield from a given amount of storage. This often occurs in the final design phases or in re-evaluation of an existing reservoir for a more comprehensive analysis. The purpose of this study is to improve the present methodology estimating the storage-yield relationship for a reservoir design or a reservoir operation. The Residual Mass curve Technique, the slightly modified version of Low Flow Techniques and the Transition Probability Matrix Technique are reviewed and examined for the best fit technique to find the reservoir storage-yield realtionship. The historical data during 1917~1940 at the proposed Hongchun damsite and the synthetic data simulated by Thomas-Fiering model are utilized to examine the reservoir storge-yield relationship with three techniques in detail. After the three techniques which estimate the reservoir storage-yield relationship were reviewed extensively, it was concluded that the Residual Mass Curve Technique and the slightly modified version of Low Flow Techniques were suitable for a preliminary design, but the Transition Probability Matrix Technique Provided satisfactory results as a final design technique because it reflected the variation of a monthly yield as well as seasonlly.

근본적으로 저수지의 Storage-Yield 관계를 해석하는 데는 두가지 관점이 있다. 가장 보편적인 관점은 필요한 수요량을 공급하기 위하여 저수지의 필요저수용량을 결정하는 것이다. 이런 형태의 문제는 저수지의 계획이나 초기 설계단계에서 보통 생긴다. 두 번째 관점은 주어진 저수용량에 대한 방류량의 결정이며, 이것은 최종 설계나 더 상세한 분석을 위한 현존 저수지의 재평가에서 자주 생긴다. 본 연구의 목적은 저수지의 설계나 운영을 위한 Storage-Yield 관계를 산정하는 현재의 방법론을 개선하는 것이다. 저수지의 Storage-Yield 관계를 해석하느 s가장 적합한 기법을 찾기 위하여 잔차누가곡선기법(Residual mass curve technique), 개선된 저류량기법(Low flow technique)과 TPM 기법(Transition probability matrix technique)이 검토되었다. 저수지의 Storage-Yield 관계를 해석하는데 있어서 홍천댐 건설예정지점의 1917∼1940년 월유입량 자료와 Thomas-Fiering 모델에 의해 모의 발생된 자료를 가지고 위의 세가지 기법을 상세히 검토하였다. 저수지의 Storage-Yield 관계를 폭넓게 검토한 결과, 잔차누가곡선기법과 저류량기법은 예비 설계에 타당하며, TPM 기법은 월별 혹은 계절별 수요변동을 고려할 수 있기 때문에 최종 설계에 타당한 기법임을 알 수 있다.

Keywords