A Study on Loading in Flexible Manufacturing System

유연생산시스템에서 작업할당에 관한 연구

  • 임재우 (한양대학교 산업공학과) ;
  • 노인규 (한양대학교 산업공학과)
  • Published : 1999.05.01

Abstract

This study is concerned with the loading problems in flexible manufacturing system(FMS). The loading problem in FMS is a complex one, when the number of machine and job is increased. It may be time-consuming and even impossible to achieve an optimal solution about this problem mathematically. Thus, a heuristic method is recommended in order to gain near-optimal solutions in a practically acceptable time. A new loading algorithm is developed with a multi-criterion objective of considering the workload unbalance, and maximizing the machine utilization, throughput for critical resources such as the number of tool slots and the number of working hours in a scheduling period and so on. The results of SAS analysis indicated that true average throughput of proposed heuristic loading statistically exceeds that of Shanker and Srinivasulus loading algorithm at the significance level of 0.1.