Abstract
The purpose of this paper is to present the pressuremeter test result and analysis for Yulchon Combined Cycle Power Plant(CCPP) site. The CCPP site is old backfill area with the hillcut materials obtained from the borrow sources near the mountains. The geology of this area consists of 6-layers from the ground level such as hillcut material, dredged clay fill, silty sand, original marine clay, weathered rock, soft rock, etc.. The pressuremeter test has been carried out with three different probe, in size and membrane type for all layers except the clay layers. The cone penetration test has been also carried out to collaborate with the pressuremeter test in the hillcut material layer.
본 논문의 목적은 율촌 복합화력발전소 부지에 대한 지지력 산정 및 지반 특성 파악을 위한 공내재하시험의 결과를 분석하는 것이다. 율촌 복합화력발전소 부지는 인근의 야산 토취장에서 매립토를 채취 운반하여 강제치환공법으로 성토하였으며, 지질은 상부로부터 산토, 준설매립해성점토, 실트집모래, 원지반해성점토층, 풍화대, 풍화암, 연암의 순으로 존재한다. 공내재하시험은 해성점성토층을 제외한 토층에 대하여 토층의 특성에 따라 각각 다른 크기의 Probe와 Membrane을 사용하여 수행하였으며, 콘시험과의 상관성, 내부 마찰각과의 관계 및 토질 특성을 파악하였다.
Keywords