Abstract
Computer simulations were performed for Heating Ventilating and Air-Conditioning (HVAC) systems to figure out more efficient maintenance methods for the building used for adolescent trainees. This study aims at suggesting design alternatives for optimum operation and performing life cycle cost (LCC) for each alternative. First, the capacity of the heat source equipment was determined using annual maximum heating and cooling loads. Annual loads were calculated and applied to the alternative for the purpose of calculating annual energy cost. Second, several types of data were collected to predict energy cost. Finally, the pay back period for each alternative was calculated using total cost estimation during standard duration period. This study indicates that the absorption chiller that does not occupy most part of a mechanical room, and does not need much operation cost was most economical.