Abstract

A firm decides to go to the project based on its investment analysis. However, the cash flows generated from the real project can not be always coincident with what expected as it follows uncertain behavior and the asymmetric payoff caused by the managerial flexibilities involved in the real asset affects the project value. Amongst various managerial flexibilities entailed in most of the real assets, although investment delay has been known to enhance the project value thanks to its ability to provide new market information to management, the related research to select the time to invest have been just few. Therefore, this research aims to show the theoretical framework to decide when to invest reflecting the behaviors of increasing project value and loss recovery cost due to investment delay with option pricing, related financial economic, and variational theories.

기업은 이익창출을 위해 자본과 비용을 투입하고 재무적 타당성을 분석하여 투자의 가부를 결정한다. 일반적으로 실물자산의 투자가 창출하는 현금흐름은 투자분석시의 결과와는 달리 불확실하게 변화하고 실물자산이 내포한 여러 경영상의 유연성이 유발하는 비대칭수익구조도 사업의 가치에 영향을 미친다. 실물자산의 투자가 수반하는 다양한 경영상의 유연성들 중, 경영진이 특정 기간 동안 투자를 지연할 수 있는 투자지연의 의사결정은 시장에서 새로운 정보가 유입되면 합리적인 대응을 가능케하여 사업의 가치를 증가시키는 것으로 알려져 왔으나 투자시기의 결정에 관한 연구는 부족해왔다. 그러므로 본 연구는 투자지연이 유효한 실물자산의 투자에서 합리적인 투자시기의 결정을 위해 투자지연에 의한 사업가치의 증분과 손실회복비용을 옵션 가격결정 및 관련 금융 경제이론에 기반하여 추정하고 이를 수학적 변분원리를 이용하여 최적의 투자시기 탐색을 위한 이론 모델을 구성 한 후 부동산 실물자산인 REITs(Real Estate Investment Trusts)의 사례에 적용 및 분석함으로써 실물자산의 투자시기 결정을 위한 이론적인 틀을 제시하고자 한다.

Keywords

References

  1. Amram, M. and Kulatilaka, N. (1999). Real Options: Managing Strategic Investment in an Uncertain World, Harvard Business School Press, Cambridge.
  2. Black, F. and Scholes, M. (1973)." The pricing of options and corporate liabilities."Journal of Political Economy, 81, pp. 637-654. https://doi.org/10.1086/260062
  3. Boer, F. P. (2003). "Risk-adjusted valuation of R&D projects."Research Technology Management, Sep/Oct, pp. 50-58.
  4. Bowen, M. G. (1987). "The escalation phenomenon reconsidered: decision dilemmas or decision errors?" Academy of Management Review, 12, pp. 52-66. https://doi.org/10.5465/AMR.1987.4306470
  5. Brigham, E. F. and Houston, J. F. (2004). Fundamentals of Financial Management, 10thed., Thomson South- Western, Mason, O.H.
  6. Cross. R. (1993). "Hysteresis and post keynesian economics."Journal of Post Keynesian Economics, 15(3), pp. 305-308. https://doi.org/10.1080/01603477.1993.11489945
  7. Davidson, P. (1993). "The elephant and the butterfly: or hysteresis and post keynesian economics." The Journal of Post Keynesian Economics, 15(3), pp. 309-321. https://doi.org/10.1080/01603477.1993.11489946
  8. Dixit, A. K. (1989). "Entry and exit decisions under uncertainty." Journal of Political Economy, 97, pp. 620-638. https://doi.org/10.1086/261619
  9. Dixit, A. K. (1992)." Investment and hysteresis." Journal of Economic Perspectives, 6(1), pp. 107-132. https://doi.org/10.1257/jep.6.1.107
  10. Dixit, A. K. and Pindyck, R. S. (1994). Investment under Uncertainty, Princeton Univ. Press, Princeton.
  11. Katzner, D. W. (1993). "Some notes on the role of history and the definition of hysteresis and related concepts in economic analysis." Journal of Post Keynesian Economics, 15(3), pp. 323-345. https://doi.org/10.1080/01603477.1993.11489947
  12. Kelly, M. (1991)." The value of the option to wait and see." Economic Letters, 36, pp. 147-151. https://doi.org/10.1016/0165-1765(91)90180-S
  13. Luehrman, T. (1997)." What's it worth? a general managers guide to valuation." Harvard Business Review, 75(3), pp. 132-142
  14. MacDonald, R. and Siegel, D. (1986)." The value of waiting to invest." The Quarterly Journal of Economics, 101(4), pp. 707-727. https://doi.org/10.2307/1884175
  15. Marshall, A. (1949). Principles of Economics, 8th ed., The Macmillan Press, London.
  16. Mello, A. S. and Pyo, U. (2003)." Real options with market risks and private risks." Journal of Applied Corporate Finance, 15(2), pp. 89-101.
  17. Miller, L. T. and Park, C. S. (2002)." Decision making under uncertainty-real options to the rescue." The Engineering Economist, 47(2), pp. 105-150. https://doi.org/10.1080/00137910208965029
  18. Moon, J. (2002). Real Options Analysis: Tools and Techniques for Valuing Strategic Investments and Decision, John Wiley & Sons, Inc., N.J.
  19. Myers, S. C. (1977)." Determinants of corporate borrowing." Journal of Financial Economics, 5(Nov), pp. 147-175. https://doi.org/10.1016/0304-405X(77)90015-0
  20. Myers, S. C. (1984)." Finance theory and financial strategy." Interfaces, 14(1), pp. 126-137. https://doi.org/10.1287/inte.14.1.126
  21. Park, C. S. and Herath, H. S. B. (2000). "Exploiting uncertainty-investment opportunities as real options: a new way of thinking in engineering economics." The Engineering Economist, 45(1), pp. 1-36. https://doi.org/10.1080/00137910008967534
  22. Pindyck, R. S. (1991). "Irreversibility, uncertainty, and investment." Journal of Economic Literature, 29(3), pp. 1110-1148.
  23. Rockafellar, R. T. and Wets, R. J-B. (1998). Variational Analysis, Springer, Berlin.
  24. Smith, J. E. and McCardle, K. F. (1998). "Valuing oil properties: integrating option pricing and decision analysis approaches." Operations Research, 46(2), pp. 198-217. https://doi.org/10.1287/opre.46.2.198
  25. Trigeorgis, L. (1999). Real Options-Managerial Flexibility and Strategy in Resource Allocation, The MIT Press, Cambridge.
  26. Yao, J. and Jaafari, A. (2003)." Combining real options and decision tree: an integrative approach for project investment decisions and risk management." The Journal of Structured and Project Finance, Fall, pp. 53-69.

Cited by

  1. Prediction of Occurring Time of Construction Firm's Contingent Liability in Real Estate Project Finance under Loan Agreement vol.30, pp.12, 2014, https://doi.org/10.5659/JAIK_PD.2014.30.12.235