Analysis of Boundary Conditions for Activities' Relationships in Linear Scheduling Model

선형 공정계획 모델의 액티비티 관계의 경계조건 분석

  • 류한국 (국립창원대학교 건축공학과) ;
  • 김태희 (국립목포대학교 건축공학과)
  • Received : 2010.04.26
  • Accepted : 2010.08.26
  • Published : 2011.01.31

Abstract

Domestic leading construction companies has been establishing and performing TACT scheduling method, similar to linear scheduling model such as line of balance and repetitive schedule, and etc. in which repetitive construction works are involved like high-rise building. Linear scheduling model has been researched as a visual scheduling method presenting the work space and time information. Likewise scheduling constraints of CPM network such as finish-to-finish, start-to-start, finish-to-start, start-to-start, linear scheduling model also has the relationships constraints, namely boundary conditions, between activities. It is especially necessary to define the boundary conditions of the activities' relationships in order to apply the linear scheduling model to be compatible with the network schedule. Therefore, this research considers the boundary conditions between activities for establishing the linear scheduling model. This paper also applies the proposed boundary conditions to TACT schedule and then deduces the main considerations in order to establish and perform TACT schedule.

국내 일부 건설사는 초고층 건축공사와 같이 반복 공종이 많은 건축물에 일종의 선형 공정계획인 택트 공정계획을 수립하고 수행하고 있다. 선형 공정계획 모델(Linear Scheduling Model: LSM)은 작업 공간과 시간의 정보를 제공하는 시각적 도구로써 연구가 되어왔다. CPM 네트워크 공정표의 구속조건(종료 후 종료, 시작 후 종료, 종료 후 시작, 시작 후 시작)과 마찬가지로 선형계획모델 또한 작업간의 관계간의 구속조건이 발생한다. 특히, 네트워크 공정표를 호환하기 위하여 작업간의 중요 속성간의 관계성의 경계 조건을 정의하는 것이 필요하다. 따라서 본 연구는 선형 공정계획을 수립 시 발생하는 액티비티간의 공간상의 경계조건을 분석한다. 또한 선형 공정계획의 액티비티 간의 관계성을 고려하여 현재 일부 건설회사를 중심으로 사용하고 있는 택트 공정계획에 제안한 경계조건을 반영하여 택트 공정계획 수립과 관리를 위해 고려해야 하는 주요 사항을 제시하는 것이 본 연구의 목적이다.

Keywords

References

  1. 김선국 외 5인(2003), "작업일보 정보를 이용한 택트공정관리방안 연구", 한국건설관리학회 논문집, 4(4), pp.80-87.
  2. 김영재 외 5인(2003)," 건축공사 마감공기 단축을 위한 택트공정 관리 프로세스 모델", 대한건축학회 논문집(구조계), 19(1), pp.161-168.
  3. 김지헌 외 3인(2007), "작업흐름 기반의 택트공정관리 프로세스", 대한건축학회 논문집(구조계), 23(6), pp.153-162.
  4. 박민선 외 3인(2006)," 제약이론을 이용한 택트공정관리 개선에 관한 연구", 대한건축학회 논문집(구조계), 22(6), pp.139-146.
  5. 서상욱 외 4인(2003), "TACT 공정관리 시스템 개발 및 적용 사례", 한국건설관리학회 논문집, 4(4), pp.145-154.
  6. 신범열(2008), "[공사기록] 초고층 오피스 빌딩의 첨단 시공/엔지니어링 기술 적용 사례", 한국건축시공학회, pp.6-16.
  7. 신동호 외 3인(2010)," 공동주택 마감공사의 TACT 프로세스 적용방안", 대한건축학회 논문집(구조계), 26(01), pp.129-136.
  8. 윤유상과 서상욱(2003), "공동주택 마감공사에서의 택트공정관리 적용에 관한 연구", 한국건설관리학회 학술발표대회 논문집(제4회), pp.422-445.
  9. 윤유상과 서상욱(2005), "건축마감공사에서의 택트타임 설정을 통한 작업 조정 프로세스 개발", 한국건설관리학회 논문집, 6(6), pp.90-97.
  10. 윤유상 외 5인(2003)," 작업구역의 합리적 분할에 의한 건축 마감공사의 공정운영 개선", 한국건설관리학회 논문집, 4(2), pp.59-65.
  11. 이재섭(2008)," 학습효과와선형계획법을이용한건설공사공기 지연 분석방법", 대한건축학회 논문집(구조계), 24(5), pp.185-192.
  12. El-Rayes,K.(2001), "Object-oriented model for repetitive construction scheduling", J.Constr. Engrg. and Mgmt., ASCE, 127(3), pp.199-205. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:3(199)
  13. Liu, S. S.(1999), "Resource-constrained scheduling of linear projects: A heuristic approach using Tabu search heuristics." Phd thesis, Purdue University, West Lafayette, Ind.
  14. Mattila, K. G.(1997)," Resource leveling of linear schedules: A mathematical approach using integer linear programming." PhD thesis, Purdue University, West Lafayette, Ind.
  15. Mulholland, B. and Christian, J.(1999), "Risk assessment in construction schedules", J.Constr.Engrg. and Mgmt.,ASCE, 125(1), pp.8-15. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:1(8)
  16. Reda, R. M.(1990)," RPM : Repetitive project modeling", J. Constr. Engrg. and Mgmt., ASCE, 116(2), pp.316-330. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:2(316)
  17. Suhail, S. A., and Neale, R. H.(1994), "CPM/LOB. New methodology to integrate CPM and line of balance", J. Constr. Engrg. and Mgmt., ASCE, 120(3), pp.667-684. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:3(667)
  18. Thabet, W. Y. and Beliveau, Y. J.(1994a), "HVLS: Horizontal and Vertical Logic Scheduling for multistory projects"J.Constr.Engrg. and Mgmt.,ASCE, 1994a, 120(4), pp.875-892. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(875)
  19. Thabet, W.Y., Believeau, Y.J.(1994b), "Modeling work space to schedule repetitive floors in multistory buildings", J. Constr. Engrg. and Mgmt., ASCE, 120(1), pp.96-116. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(96)
  20. Wikipedia(2006)

Cited by

  1. Developing Crew Synchronization System for Repetitive Units vol.30, pp.12, 2014, https://doi.org/10.5659/JAIK_SC.2014.30.12.45