Quantified Impact Analysis of Construction Delay Factors on Steel Staircase Systems

  • Received : 2012.09.13
  • Accepted : 2012.10.23
  • Published : 2012.12.20

Abstract

Construction projects have become so large, complicated and incredibly high-tech that process management is currently considered one of the most important issues. Unlike typical manufacturing industries, most major construction activities are performed in the open air and thus are exposed to various environmental factors. Many studies have been conducted with the goal of establishing efficient techniques and tools for overcoming these limitations. Productivity analysis and prediction, one of the related research subjects, must be considered when evaluating approaches to reducing construction duration and costs. The aim of this research is to present a quantified impact analysis of construction delay factors on construction productivity of a steel staircase system, which has been widely applied to high rise building construction. It is also expected to improve the process by managing the factors, ultimately achieving an improvement in construction productivity. To achieve the research objectives, this paper analyzed different delay factors affecting construction duration by means of multiple regression analysis focusing on steel staircase systems, which have critical effects on the preceding and subsequent processes in structure construction. Statistical analysis on the multiple linear regression model indicated that the environment, labor and material delay factors were statistically significant, with 0.293, 0.491, and 0.203 as the respective quantified impacts on productivity.

Keywords

References

  1. Han SW, Lee SY. Quantified comparison and analysis of different productivity measurements. Journal of Asian Architecture and Building Engineering. 2008 Nov;7(2):309-16. https://doi.org/10.3130/jaabe.7.309
  2. Han SW, Hong TH, Kim GH, Lee SY. Technical comparisons of simulation-based productivity prediction methodologies by means of estimation tools focusing on conventional earthmovings. Journal of Civil Engineering and Management. 2011 June;17(2):265-77. https://doi.org/10.3846/13923730.2011.574381
  3. Lee YM, Kim YS. A study for major delay risk factors in curtain wall work of high-rise building using FMEA. Journal of the architectural institute of Korea : Structure & construction 2011 Jan;27(1):189-96.
  4. Song JW, Yu JH, Kim CD. Work condition analysis process for improving reliability of work plan. Korean Journal of Construction Engineering and Management 2009 Jan;10(1):36-44.
  5. Halpin DW, Woodhead RW. Construction management. 2nd ed. NewYork (NY): John Wiley & Sons;1998. 444 p.
  6. Jang JS, Shin YS, Kang KI. A work process for productivity improvement of concrete structural frame work in tall building. Proceedings of the Korea Institute of Building Construction. 2005 May; Seoul National University of Science & Technology. Seoul (Korea): the Korea Institute of Building Construction; 2005. p. 161-4.
  7. Lee JH. Construction performance evaluation of an advanced-technology based on construction simulation technique [master's thesis]. Incheon (Korea): Inha University; 2010. 71 p.
  8. Lee JH, Lee KS, Kim HM, Kim YS, Han SW. Construction performance evaluation of steel staircase systems based on construction simulation CYCLONE techniques. Journal of the Korea Institute of Building Construction. 2010 Dec;10(6):19-26. https://doi.org/10.5345/JKIC.2010.12.6.019
  9. Kim HY, Kim TH, Shin YK, Kim YS, Han SW. Regression technique-based productivity estimation conducting construction delay factor analysis on interior works in high-rise building construction. Proceedings of the Korea Institute of Building Construction. 2011 May; Dong-Eui University. Busan (Korea): the Korea Institute of Building Construction; 2011. p. 191-2.
  10. Adrian JJ, Boyer LT. Modeling method productivity. Journal of the Construction Division. 1976 Mar;102(1):157-68.
  11. Halpin DW, Riggs LS. Planning and analysis of construction operations. NewYork (NY): John Wiley & Sons; 1992. 381 p.
  12. Han SW. A case study for delay analysis by means of method productivity delay model. The 6th International Symposium on Architectural Interchanges in Asia; 2006 Oct; Daegu (Korea). Seoul (Korea): Architectural Institute of Korea; 2006. p. 1367-70.
  13. Seo HS, Yang KS, Kim NY, Kim HY, Kim MK. SPSS(PASW) regression analysis. 3rd ed. Seoul (Korea): Hannarae Publishing Co.; 2009. 486 p. Korean.
  14. Smith, SD. Earthmoving productivity estimation using linear regression techniques, Journal of Construction Engineering and Management. Journal of Construction Engineering and Management. 1999 May/June;125(3):133-41. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(133)
  15. Smith SD, Wood GS, Gould M. A new earthworks estimating methodology. Journal of Construction Management and Economics. 2000 Oct;18(2):219-28. https://doi.org/10.1080/014461900370843
  16. Han SW, Hong TH, Lee SY. Production prediction of conventional and global positioning system-based earthmoving systems using simulation and multiple regression analysis. Canadian Journal of Civil Engineering. 2008;35(6):574-87 https://doi.org/10.1139/L08-005
  17. Han SW. Productivity analysis comparison of different types of earthmoving operations by means of various productivity measurements. Journal of Asian Architecture and Building Engineering. 2010 May;9(1):185-92. https://doi.org/10.3130/jaabe.9.185
  18. Jeon SH, Koo KJ. Comparison of labor inputs from standard quantities per unit and actual quantities in apartment reinforced concrete work. Korean Journal of Construction Engineering and Management. 2008 Apr;9(2):182-9.
  19. Adrian JJ. Quantitative methods in construction management. American Elsevier. New York (NY): American Elsevier; 1973. 491 p.
  20. Lee KS, Lee JH, Kim HM, Kim YS, Han SW. Productivity analysis of steel staircase systems utilizing simulation Method. Proceedings of the Korea Institute of Building Construction; 2010 May; Hanyang University. Seoul (Korea): the Korea Institute of Building Construction; 2010. p. 101-4.