A Study on the Improvement of Railway Construction Schedule Using KTX Construction Case

경부고속철도 사례분석을 통한 철도건설공기 개선에 관한 연구

  • Yang, Yeonjong (Construction Headguarters/Conventional Railway Division, Korea Rail Network Authority) ;
  • Chung, Byunghyun (Department of Trasportation and Logistics, Woosong University)
  • Received : 2012.11.07
  • Accepted : 2012.11.28
  • Published : 2012.12.31

Abstract

In 2004, KTX operated in Korea on the 5th in the world. But there are various factor on planed schedule delay of Big National Construction Project like Seoul-Busan High Speed Rail Project(Seoul-Busan HSR). For example, Often change of government policy, project management control problem of design and construction, conflict of interested party like environmental organization/resident are the main delay factors. The suggestions for improvement of the construction schedule through the Seoul-Busan HSR will help to make a new leap forward in rail construction.

2004년에 세계에서 5번째로 한국에서 고속철도를 운영하게 되었으며, 2011년 서울~부산간 전구간의 철도건설이 완공되어 고속철도가 운행되고 있다. 경부고속철도와 같은 대형국책사업에 있어 계획된 공기에 영향을 미치는 요소는 다양하였다. 국내에서는 처음으로 시행된 고속철도 건설사업으로서 본 사업과정상에 잦은 국가정책의 변경, 설계 및 시공상 사업관리의 어려움, 환경단체나 지역주민 등 이해관계자와의 갈등 등이 철도건설공기에 영향을 주는 주요 요소로 볼 수 있으며 경부고속철도를 통해 경험한 지연요소에 대한 종류, 문제점 등을 분석하여 향후 대형국책사업 등의 시행에 있어서 사업관리 및 추진의 효율성 향상에 기여하고자 한다. 특히, 사업단계에서부터 철저한 공기관리가 필요하며, 아울러 최근 중요시되는 환경문제 등에 관해서는 사업전반에 걸쳐 관리가 필요한 것으로 나타났다.

Keywords

References

  1. C.H. Na (2007) A Study on the Construction and Operation System Improvement for Metropolitan Rapid Railroads, Master Thesis, Daejin University, pp. 57-60.
  2. S.K. Back (1995) A Study on the financing plans for metropolitan railway construction focusing on Seoul Metropolitan Area, Master Thesis, Seoul National University, pp. 90.
  3. M.C. Lee (2009) A Study on Conflict of The Construction of Yangsan Route in the Seoul-Busan High-speed Railway, Master Thesis, Ulsan University, pp. 70.
  4. Y.P. Hong (2007) A Study on the Resolution of public conflict through the participation of residents, Master Thesis, Dongkuk University, pp. 142-145.
  5. S.H. Lee (2004) A Study on the Analysis Methodologies of Delay Influence Factors in Construction of Korea High Speed Railway, Master Thesis, Yonsei University, pp. 163-170.
  6. Korea Rail Network Authority(2011), The History of Kyungbu Highspeed railway construction III-1,2.
  7. Korea Rail Network Authority (2010) Railway business Description Material of 2011.
  8. Korea Chamber of Commerce & Industry (2005) Major national business interruption case analysis and implications.
  9. Y.S. Lee., D.S. Moon (2007) A Study on the development of High Speed Rail(HSR) and its influence, Journal of the Korean Society for Railway, 10(1), pp. 23-37.
  10. Korea Rail Network Authority (2010) Railway Plan & Construction, pp. 25-78.
  11. Korea Rail Network Authority (2009) The Conflict resolution casebook of Public business, pp. 90-108.