Development of the Approximate Cost Estimating Model Using Statistical Inference for PSC Box Girder Bridge Constructed by the Incremental Launching Method

통계적 기법을 활용한 ILM압출공법 교량 상부공사 개략공사비 산정모델 개발 연구

  • Kim, Sang-Bum (Dongguk University, Civil and Environmental Engineering) ;
  • Cho, Ji-Hoon (Dongguk University, Civil and Environmental Engineering)
  • 김상범 (동국대학교 건설환경공학과) ;
  • 조지훈 (동국대학교 건설환경공학과)
  • Received : 2012.12.18
  • Accepted : 2013.01.02
  • Published : 2013.03.30

Abstract

This research focuses on development of the conceptual cost estimation models for I.L.M box girder bridge. The current conceptual cost estimation for public construction projects is dependent on governmental average unit price references which has been regarded as inaccurate and unreliable by many experts. Therefore, there have been strong demands for developing a better way of conceptual cost estimating methods. This research has proposed three different conceptual cost estimating method for a P.S.C. girder bridge built with the I.L.M method. Model (I) attempts to seek the proper breakdown of standard works that are accountable for more than 95 percentage in total cost and calculates the amount of standard work's materials from the standard section and volume of I.L.M box girder bridge. Model (II) utilizes a correlation analysis (coefficient over 0.6 or more) between breakdown of standard works and input data that would be considered available information in preliminary design phase. Model(III) obtains conceptual estimating through multiple-regression analysis between the breakdown of standard works and all of input data related to them. In order to validate the clustering of coverage in the preliminary design phase, the variation of I.L.M cost coverage from multiple-regression analysis[model(III)] has been investigated which result in between -3.76% and 11.79%, comparing with AACE(Association for the Advancement of Cost Engineering) which informs its variation between -5% and +15% in the design phase. The model proposed from this research are envisioned to be improved to a great distinct if reliable cost date for P.S.C. girder bridges can be continually collected with reasonable accuracies.

본 연구에서는 평균건설단가를 적용하여 개략 공사비를 산출하는 기존 방식에서 벗어나 대표공종을 이용한 입력변수 도출 모델을 구축하여 기본설계단계에서 고려되어지는 여러 입력변수들을 활용하여 P.S.C(Prestressed Concrete) Box Girder 교량에서 널리 활용되고 있는 I.L.M(Incremental Launching Method) 공법에 연구 모델을 적용하고자 한다. 2000년부터 설계된 공사비 데이터와 설계자료 등을 분석하여 상부공사 중 총 공사비대비 누적비율 95%이상을 차지하는 공종을 대표공종으로 도출하였다. 각 대표공종의 하위공종에 대한 내역 분기를 실시하여 각 항목들의 Database를 구축하였다. 본 연구에서는 다각적인 측면에서 개략공사비 산정 모델을 개발 및 제시하였으며, 사용자 입장에서 보다 쉽게 접근할 수 있도록 대표공종을 기초로 단위물량을 사용한 개략공사비 산정모델(I)과 상관성이 높은 입력변수를 선택한 개략공사비 산정모델(II)과 상관계수 0.6이상의 입력변수들을 모두 포함하는 다중회귀분석을 통한 개략공사비 산정모델(III)을 제시한다. 실제 총공사비와 본 연구에서 제시하는 개략공사비 산정모델들을 비교하고, 신뢰성을 검증함으로써 현재 국내에서 사용되는 산정방법에 비해 정밀도 측면에서 효율적인 공사비 관리방법을 제시한다.

Keywords

References

  1. Bruce L. Bowerman et al.(2004), "Business Statistics".
  2. MOCT. (2007a). "Guideline for investment evaluation," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
  3. MOCT. (2007b). "Guide for road construction," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
  4. KDI. (2004). "Guideline for preliminary feasibility study; Road and Railway-Ver. 4," Korea Development Institute, Seoul (in Korean).
  5. Park, J. H. and Lee, T. S. (2003). "Methodology for a cost estimating on the project of a composite facility." Journal of the Korean Society of Civil Engineering," KSCE, Vol. 23, No. 1-D, pp. 69-78.
  6. Lee, Y. S. (2003). "Development of construction cost model through the analysis of critical work items." Journal of Construction Management," KICEM, Vol. 4, No. 4, pp. 212-219.
  7. Trost, S. M. and Oberlender, G. D. (2003). "Predicting accuracy of early cost estimates using factor analysis and multivariate regression," Journal of Construction Engineering and Management, ASCE, Vol. 129, No. 2, pp. 198-204. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(198)
  8. Kyong Ju Kim, Kyoungmin Kim, and Chan Sung Kang(2009) "Approximate Cost Estimating Model for PSC Beam Bridge Based on Quantity of Standard Work," Journal of Civil Engineering, Korean Society of Civil Engineers, 13(6), 2009. 11. pp. 377-388 (in Korean). https://doi.org/10.1007/s12205-009-0377-0
  9. Kyong Ju Kim, Kyoungmin Kim(2010), "Preliminary Cost Estimation Model Using Case-Based Reasoning and Genetic Algorithms," Journal of Computing in Civil Engineering, American Society of Civil Engineers, 24(6), 2010. 11. pp. 499-505. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000054
  10. Kang, C.S, Lim W.S., Kim K.M and Kim K.J(2007), "Approximate Estimating Model for PSC BEAM Bridge Using Influence Factors," KICEM (2007-11).
  11. Kang, C.S, Lee G.H, Kim K.M and Kim K.J.(2008), "Approximate Estimating Model Using the Case Based Reasoning," KICEM (2008-11).
  12. Park, J. H. and Lee, T. S. (2002). "Development of the cost analysis format for road construction project." Journal of Civil Engineering," KSCE, Vol. 22, No. 2-D, pp. 259-269.
  13. Hong T.H.(2008), "Cost prediction model of Public Multi-housing Projects in Schematic Design Phase," KICEM, Vol. 9, No. 3 pp. 65-74.
  14. Park M.S.(2008), "Method of Quantity Data Analysis for Building Construction Cost Estimation : Focusing on Finish Work of Public Apartment Project," KICEM, Vol. 9, No. 6, pp. 235-243.
  15. MOCT.(2007), "Civil Quantity Works calculated based on guidelines," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
  16. Kim K. J.(2007), "Quantity - Theory and Practice," Gumi Books (in Korean).
  17. Ministry of Land. Transport and Marine Affairs(2004), "Volume reduction through the advancement of PSC box girder bridge design".
  18. Cho, J. H.(2008), "Development of an Activity-Based Conceptual Cost Estimating Model for P.S.C Box Girder Bridge," KICEM (2008-11).
  19. Park S. H.(2008), "Object & Parameter based Schematic Estimation Model for Predicting Cost of Building Interior Finishings," KICEM, Vol. 9, No. 6, pp. 175-184.
  20. Jung, Y. H.(2004), "Static Data Analysis".
  21. Jang, S. K.(2006), "Basic Static Data Analysis".
  22. Kim D. S.(2008), "Regression analysis Fundamentals and Applications" pp. 209-228.
  23. KICT(2011), "Development of Cost Estimating Model; Bridge and Tunnel," Research Report.