Development of the Approximate Cost Estimating Model for PSC Box Girder Bridge based on the Breakdown of Standard Work

대표공종 기반의 PSC Box 교량 상부공사 개략공사비 산정모델에 관한 연구

  • Kim, Sang-Bum (Dongguk University, Civil and Environmental Engineering) ;
  • Cho, Ji-Hoon (Dongguk University, Civil and Environmental Engineering)
  • 김상범 (동국대학교 건설환경공학과) ;
  • 조지훈 (동국대학교 건설환경공학과)
  • Received : 2012.12.18
  • Accepted : 2013.01.02
  • Published : 2013.03.30

Abstract

Needs for developing a better way of cost estimating process for public construction projects have been widely recognized. Those needs are mainly from the early phases of the project through the construction life cycle due to the its importance to the control process. In contrast to the traditional estimating method based on unit-price references, this research utilized this following process. The first step is analyzing the real cost data from actual cost activities (2000~2010) about the statement of P.S.C(Prestressed Concrete) Box Girder Bridge. The collected data was broken into four categories based on technical construction methods such as I.L.M(Incremental Launching Method), M.S.S(Movable Scaffolding System), F.S.M(Full Staging Method), and F.C.M(Free Cantilever Method). The second, actual design documents including the actual cost estimating documents, drawings and specifications were carefully reviewed to cluster the cost itemized statement from four categories. It was also attempted to seek the proper breakdown of standard works that are responsible for more than 95 percentage in each categories in terms of its cost. The third, this research comes up the index for standard unit materials and unit price of standard work and develops the approximate estimating model applying for the specification(length and breadth of bridges) per square area that the user takes as well as suggests the practical application plan within the original time alloted.

국내 도로 건설사업의 사업초기단계에서의 개략공사비 산정은 예비타당성조사, 도로업무편람, 투자평가지침에서 제시하는 도로의 평균단가 또는 표준단가를 기준으로 도출되는데 이는 공사비 산정 표준체계 부재 및 기초자료 갱신 평균단가를 적용하여 공사비를 산출하는 방식으로 본 연구의 대상인 특수 교량공사의 특성을 전부 반영하기에 미흡한 실정이다. 또한, 신속한 의사결정이나 대안선택이 결정되는 설계단계에서 소모적이고 획일적인 공사비 산정방식의 한계점을 개선하고 사업초기단계의 개략공사비산정 프로세스의 효율성 및 신뢰도를 높이기 위한 새로운 공사비 산정 모델을 개발이 요구된다. 이에 본 연구에서는 평균건설단가를 적용하여 개략 공사비를 산출하는 기존 방식에서 벗어나 대표공종 기반의 상세물량입력 모델을 구축하였다. 실적 공사비 데이터 및 공종별 원가자료를 기반으로 토목공사 수량산출 지침서 기준 전체 공종내역 중 공사비 누적비율 대비 95%이상을 차지하는 대표적인 공종을 도출하였다. 상부면적당 대표공종기반 단위물량 및 차로수별 공사비단가를 제시하고, 이를 활용하여 교량형식별로 상부면적당 공사비단가를 도출 및 검증을 통해 사업초기단계에서 업무추진 의사결정의 신뢰적 지원 및 효율적인 공사비 산정방식을 도출 하였다.

Keywords

References

  1. MOCT. (2007a). "Guideline for investment evaluation", Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
  2. MOCT. (2007b). "Guide for road construction", Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
  3. KDI. (2004). "Guideline for preliminary feasibility study; Road and Railway-Ver. 4", Korea Development Institute, Seoul (in Korean).
  4. Park, J. H. and Lee, T. S. (2003). "Methodology for a cost estimating on the project of a composite facility." Journal of the Korean Society of Civil Engineering", KSCE, Vol. 23, No. 1-D, pp. 69-78 (in Korean).
  5. Lee, Y. S. (2003). "Development of construction cost model through the analysis of critical work items." Journal of Construction Management", KICEM, Vol. 4, No. 4, pp. 212-219.
  6. Trost, S. M. and Oberlender, G. D. (2003). "Predicting accuracy of early cost estimates using factor analysis and multivariate regression", Journal of Construction Engineering and Management, ASCE, Vol. 129, No. 2, pp. 198-204. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:2(198)
  7. Kyong Ju Kim, Kyoungmin Kim, and Chan Sung Kang(2009) "Approximate Cost Estimating Model for PSC Beam Bridge Based on Quantity of Standard Work", Journal of Civil Engineering, Korean Society of Civil Engineers, 13(6), 2009. 11. pp. 377-388. https://doi.org/10.1007/s12205-009-0377-0
  8. Kyong Ju Kim, Kyoungmin Kim(2010), "Preliminary Cost Estimation Model Using Case-Based Reasoning and Genetic Algorithms", Journal of Computing in Civil Engineering, American Society of Civil Engineers, 24(6), 2010. 11. pp. 499-505.
  9. Kang, C.S, Lim W.S., Kim K.M and Kim K.J(2007), "Approximate Estimating Model for PSC BEAM Bridge Using Influence Factors", KICEM (2007-11).
  10. Kang, C.S, Lee G.H, Kim K.M and Kim K.J.(2008), "Approximate Estimating Model Using the Case Based Reasoning", KICEM (2008-11).
  11. Park, J. H. and Lee, T. S. (2002). "Development of the cost analysis format for road construction project." Journal of Civil Engineering", KSCE, Vol. 22, No. 2-D, pp. 259-269 (in Korean).
  12. Hong T.H.(2008), "Cost prediction model of Public Multi-housing Projects in Schematic Design Phase", KICEM, Vol. 9, No. 3 pp. 65-74.
  13. Park M.S.(2008), "Method of Quantity Data Analysis for Building Construction Cost Estimation : Focusing on Finish Work of Public Apartment Project", KICEM, Vol. 9, No. 6, pp. 235-243.
  14. MOCT.(2007), "Civil Quantity Works calculated based on guidelines", Ministry of Construction and Transportation (MOCT), Seoul.
  15. Kim K. J.(2007), "Quantity - Theory and Practice", Gumi Books (in Korean).
  16. Ministry of Land. Transport and Marine Affairs(2004), "Volume reduction through the advancement of PSC box girder bridge design".
  17. Cho, J. H.(2008), "Development of an Activity-Based Conceptual Cost Estimating Model for P.S.C Box Girder Bridge", KICEM (2008-11) pp. 201-206.
  18. KICT(2011), "Development of Cost Estimating Model; Bridge and Tunnel", Research Report.

Cited by

  1. Estimation Model for Approximate Construction Quantities of Suspension Bridge in Early Stage vol.6, pp.4, 2015, https://doi.org/10.11004/kosacs.2015.6.4.024
  2. Development on Reconstruction Cost Model for Decision Making of Bridge Maintenance vol.17, pp.9, 2016, https://doi.org/10.5762/KAIS.2016.17.9.533