Analysis of Road Construction Projects' Escalation under Historical Data-Based Estimate System in Jeju

실적공사비가 적용된 제주도 도로공사의 물가변동률 영향 분석

  • 홍정호 ((재)한국자치경제연구원) ;
  • 이동욱 (제주대학교 토목공학과(해양과환경연구소))
  • Received : 2013.10.25
  • Accepted : 2014.01.20
  • Published : 2014.04.01

Abstract

This study has conducted case studies in order to suggest alternatives to the historical data-based estimate system. Price fluctuation calculation methods based on historial cost indexes, standard estimate and construction cost indexes were applied to 9 road construction sites in Jeju for an analysis. As a result, in 5 construction sites (about 56% of 9 sites), the index control rate calculated based upon historical data-based estimate system was higher than that calculated based upon standard estimate and construction cost indexes. Thus the establishment of the requirements for the adjustment of contract price due to price fluctuation delays, which leads to a significant difference in price fluctuation amount. And, in an analysis of construction cost indexes, the indexes for road construction were used for calculating index control rate which ranges from 2.0 to 9.4 percent, indicating the time of construction amount and price fluctuation application has a significant influence on index control rate.

본 연구는 제주특별자치도 내 실적공사비가 적용된 도로현장을 중심으로 물가변동에 따른 실적공사비 등락률 산정의 문제점을 분석하기 위하여 실시되었다. 본 연구를 위하여 제주특별자치도 내 9개 도로공사 현장을 중심으로 실적공사비방식, 표준품셈방식, 건설공사비지수방식에 따른 등락률을 비교 분석하였다. 분석결과 9개 현장 중 약 56%인 5개 현장에서 실적공사비의 지수조정률이 표준품셈과 건설공사비지수의 지수조정률에 비해 낮게 산정되었다. 이는 실적공사비가 적용됨에 따라 물가변동으로 인한 계약금액 조정 성립요건이 지연되고 있다는 것을 알 수 있으며, 이에 따라 공사 준공 전 물가변동으로 인한 계약금액 조정횟수의 감소와 함께 물가변동금액 역시 차이를 보일 수 있음을 의미한다. 또한, 건설공사비지수 사례분석 결과, 도로부문에 대한 지수를 적용하여 지수조정률을 산출하였으나 지수조정률이 2.0%~9.4%까지 산정되어 이는 공사금액 및 물가변동 적용시기에 따라 상당한 영향을 미치는 문제점이 나타났다.

Keywords

References

  1. Baek, Y. J. (2001). Improving the procedure-Adjusted Contract Sum for Price Escalation in Construction Projects, Youngnam University, Master's Thesis (in Korean).
  2. Choi, S. I, Lee, B. N., Lee, S. W. and Choi, M. S. (2006). An assessment and improvement scheme of a new cost estimation system in Korean public construction industry(II), Construction and Economy Research Institute of Korea (CERIK) (in Korean).
  3. Choi, S. I, Song, B. K. and Kim, Y. J. (2004). An assessment and improvement scheme of a new cost estimation system in Korean public construction industry, Construction and Economy Research Institute of Korea (CERIK) (in Korean).
  4. Jeong, K. C. (2008). Problems and improvement schemes to historical cost fluctuation ratio calculation according to the escalation, Master's Thesis, Chung-Ang University (in Korean).
  5. Korea Institute of Construction Technology (KICT). (1996). Research for improvements of estimating system in construction industry (IV) (in Korean).
  6. Korea Institute of Construction Technology (KICT). (2013). Trends of construction cost index (in Korean).
  7. Lee, J. S. and Choi, S. I. (2003), A study on introduction of standard estimate system, Construction and Economy Research Institute of Korea (CERIK) (in Korean).
  8. Park, Y. H. (2005). An improvement plan of contract price adjustment through the problem analysis of the current price escalation regulation in construction projects, Master's Thesis, Chung-Ang University (in Korean).
  9. Public Procurement Service (2013). Index rate of work types under standard estimate system (in Korean).

Cited by

  1. Comparative Analysis between GDP Deflator Method and Index Adjustment Rate Method on BTL Sewer Rehabilitation Projects in Jeju vol.35, pp.1, 2015, https://doi.org/10.12652/Ksce.2015.35.1.0217