Cost Performance Comparison of Project Delivery Methods in Public Sector - Focusing on Mediator Effect of Biddropping on Change Orders -

공공건설공사 발주방식에 따른 비용성과 실증비교 - 설계변경에 대한 낙찰률 매개효과를 중심으로 -

  • Moon, Hyosoo (Department of Architecture and Architectural Engineering, Seoul National University) ;
  • Lee, Hyun-Soo (Department of Architecture and Architectural Engineering, Seoul National University) ;
  • Park, Moonseo (Department of Architecture and Architectural Engineering, Seoul National University) ;
  • Lee, Bogyeong (Department of Architecture and Architectural Engineering, Seoul National University) ;
  • Joo, Seonu (Department of Architecture and Architectural Engineering, Seoul National University) ;
  • Son, Bosik (Department of Architectural Engineering, Namseoul University)
  • Received : 2015.07.17
  • Accepted : 2015.08.27
  • Published : 2015.09.30

Abstract

According to previous research, the reason why Design-Build(hereinafter "DB") outperforms Design-Bid-Build(hereinafter "DBB") in terms of cost is due to less change orders(hereinafter "COs"). However, if biddropping was low for DBB resulting into increasing COs, then it would be wrong to conclude that DB is superior due to less COs. Therefore, in order to confirm such misjudgment, the attempt to comprehensively analyze biddropping, COs and delivery method was made as previous methods had analyzed either the relationship between delivery method and COs, or biddropping and COs. This research uses path analysis, which simultaneously compares effect sizes on COs according to delivery method and biddropping based on the project type, and validated the mediator effect. The research proved that DB outperforms DBB due to less COs cannot be validated as biddropping caused a mediator effect by intervening between the delivery method and COs for specific project types. Therefore, the mechanism of delivery method acts on COs through biddropping was established. Also, the identity of biddropping was investigated in a different perspective from previous research. Based on this result, this research is expected to help determine a delivery method by considering the mediator effect of specific projects and evaluate performance.

기존연구에서 Design-Build(이하 "DB")가 Design-Bid-Build(이하 "DBB")발주방식보다 비용측면에서 우월하다고 하는 이유는 설계변경이 적기 때문이다. 그러나 만약 DBB가 낙찰률이 낮아 이것을 만회하기 위해 설계변경을 발생시켰다면, DB가 설계변경이 적기 때문에 우월하다는 것은 잘못된 판단이다. 따라서 이러한 판단의 오류를 확인하기 위해 발주방식과 설계변경, 혹은 낙찰률과 설계변경의 영향관계만 분석하던 두 종류의 연구들을 종합적으로 분석하는 것을 시도했다. 또한 경로분석기법을 통해 프로젝트 타입 별로 발주방식과 낙찰률이 설계변경에 미치는 효과크기를 동시에 비교함으로써 낙찰률의 매개효과를 검증하였다. 그 결과 특정 프로젝트 타입에서는 발주방식과 설계변경 사이에 낙찰률이 개입하여 매개효과를 발생시키고 있으므로, DB가 DBB보다 설계변경이 적기 때문에 우월하다고 판단할 수 없음을 검증하였다. 이로써 발주방식이 낙찰률을 통해 설계변경에 작용하는 원리를 밝히고, 낙찰률의 정체성을 기존 연구와는 다른 관점에서 규명하였다. 이를 바탕으로 프로젝트 특성에 따른 매개효과를 고려한 발주방식 선정과 성과측정에 도움을 줄 수 있을 것이라고 기대한다.

Keywords

References

  1. Cho, Y. S. and Cha, H. S., (2010). "A Study of Project Characteristics and Project Performance Level of Difficulty", Korean journal of Construction Engineering and Management, KICEM, 11(6), pp. 78-88. https://doi.org/10.6106/KJCEM.2010.11.6.78
  2. Fernane, J. D., (2011). "Comparison of design-build and design-bid-build performance of public university, Master Degree", M.S. Thesis, University of Nevada, Las Vegas, U.S.A.
  3. Gordon, C. M., (1994). "Choosing Appropriate Construction Contracting Method", J. Constr. Eng. Manage., 120, pp. 196-210. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(196)
  4. Hale, D. R., Shrestha, P. P., Gibson, E. and Migliaccio, G. C., (2009). "Empirical Coomparison of Design/Build and design/Bid/Build Project Delivery Methods", Journal of Construction Engineering and Management, 35, pp. 579-587.
  5. Ibbs, C. W., Kwak, Y., Ng, T. and Odabase, A. M., (2003). "Project Delivery Systems and Project Change: Quantitative Analysis", Journal of Construction Engineering and Management, 129, pp. 382-387. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:4(382)
  6. Jun, H. C. (2007). "A Study on Analyzing Current State of Contract & Change Order by Awarding Method in Public Construction Projects", M.S. Thesis, Hanyang University, Seoul, South Korea.
  7. Kim, G. S. (2010). "Structural Equation Modeling Analysis", Hannarae Publishing Co., Seoul, Korea.
  8. Kim, S. G. (2006). "Analysis on the Problems and Studies of the Improvement Plans Accompanied by the Design Change in Turn-key Project", M.S. Thesis, Gyeongsang National University, Korea.
  9. Konchar, M. and Sanvido, V., (1998). "Comparison of U.S.Project Delivery Systems", Journal of construction Engineering and Management, 124, pp. 435-444. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:6(435)
  10. Lee, E. J., Kim, K. H., Lee, Y. S. and Kim, J. J., (2007). "A Study on the Proposal of Post-Evaluation Model Through Improvement of Post-Evaluation Indicators in the Public Construction", Journal of the Architectural Institute of Korea Structure & Consturction, 23(12), pp. 133-140.
  11. Lee, H. S., Ji, S. H., Park, M. and Song, S. H., (2007). "Analyzing Characteristics of Design-Build Delivery System in Korea Using System Dydnamics Modeling", Korean journal of Construction Engineering and Management, KICEM, 8(5), pp. 119-131.
  12. Lee, M. J., Park, B. J. and Im, K. S., (2008). "A Study on the Estimation of Change Orders Impact for the Public Construction", Journal of the Korean Society of Civil Engineers, KSCE, 28(3D), pp. 363-369
  13. Lee, S. B. and Hwang, J. W. (2007). "A Study on the Causes Analysis of Change Order Claims in Design-Build", Journal of the Architectural Institute of Korea, 9(2), pp. 247-254.
  14. Lee, Y. S. (2013). "Suggestions for Improvement of Construction Project Awarding Methods in Public Sector", Korea Research Institute for Human Settlements, KRIHS, Construction Economy Articles(Winter), 75, pp. 43-54.
  15. Lee, Y. S., Kang, T. K., Shin, E. Y. and Park, W., (2013). "Comparison of Cost Performance for Delivery Methods on Public Construction Projects", Journal of the korean Society of Civil Engineers, KSCE, 33(6), pp. 2575-2582. https://doi.org/10.12652/Ksce.2013.33.6.2575
  16. Lee, Y. D. (2012). "A Study on Hybrid Approach of Deductive Case Analysis and AHP to Explore Change Orders in Construction Projects", M.S. Thesis, Hanyang University, Seoul, Korea.
  17. Lim, P. J. (2014). "A Study on the Difference Analysis of Construction Performance Results according to Successful Bid Selection Systems" M.S. Thesis, Chung-Ang University, Seoul, Korea.
  18. Ministry of government legislation (2015). Act on contracts to which the state is a party, Ministry of Strategy and Finance, Korea.
  19. Ministry of government legislation (2015). Construction contract general conditions, Administrative rule, Ministry of Strategy and Finance, Korea.
  20. Perkins, R. A., (2009). "Sources of Changes in Design.Build Contracts for a Governmental Owner", Journal of Construction Engineering and Management, 135, pp. 588-593. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:7(588)
  21. Riley, D. R., Diller, B. E. and Kerr, D., (2005). "Effects of Delivery Systems on Change Order Size and Frequency in Mechanical Construction", Journal of Construction Engineering and Management, 131, pp. 953-962. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:9(953)
  22. Ryou, S. S., (2010). "Analysis on the Claim Factors for Change Order of Turn-key Project", M.S. Thesis, Korea University, Seoul, Korea.
  23. Sung, J.Y., (2015). "An Analysis of Changing Construction Contract and Construction Defects Due to Bidding-Ratio in Lowest Bidding System", M.S. Thesis, Seoul National University, Seoul, Korea.
  24. The Seoul Institute, (2013). "A Research for Evaluating the Performance of Design-Build Delivery Method of Seoul City", R&D Report, Seoul Metropolitan Government, Korea.
  25. University of Seoul, (2006). "A Research for Evaluating the Performance of Design-Build Delivery Method", Construction & Transportation R&D Report, Ministry of Land, Infrastructure and Transport, Korea.
  26. Yoon, B. H. (2009). "Risk Assessment of Cost Increasing by Change Orders of Road Projects", M. S. Thesis, Yonsei University, Seoul, Korea.