A Study on NOS Model System for The Construction Work Planing and Management

건설 시공 계획 및 관리 업무의 적용을 위한 NOS 모델 구축 연구

  • Choi, Jaejin (Department of Civil Engineering, Kongju National University) ;
  • Park, Hongtae (Department of Civil Engineering, Kongju National University)
  • Received : 2016.01.14
  • Accepted : 2016.02.23
  • Published : 2016.03.31

Abstract

This study presented a new NOS model through the following suggestions to apply the construction work planing and management to NOS(Network Operating System). First, This study presented CIMS(construction information classification system) reflected the characteristics of facility classification - functional component classification - functional component classification - work classification - resource classification. Based on this system. this study presented how to establish PMMB(performance measurement management baseline) with proposed master target equation which analyzed the trend of performance measurement management baseline and proposed work target equation which analyzed the execution results. Finally, this study presented NOS model that can be applied to fixed price method and cost plus fee method through the theoretical verification of executive performance analysis method.

본 연구는 건설 시공 계획 및 관리 업무에 NOS를 적용하기 위하여 다음과 같은 제안을 과정을 통해서 새로운 NOS 모델을 제시하였다. 먼저, 건설공사의 특성을 반영한 시설 단위 - 구조 단위 - 시공 단위 - 자원 단위의 흐름으로 공사정보분류체계의 개념을 제시하였다. 이 체계를 근거로 네트워크의 구성하고, 성과측정관리기준선의 추이를 분석하는 기준계획시간(MT : Master Target)식과 집행실적을 분석해 주는 수정계획시간(WT : Work Target) 식을 제안하여 NOS 모델을 제시하기 위한 성과측정 관리 기준선의 수립방법을 제안하였다. 최종적으로 성과측정 집행 분석 방법의 이론적 검증을 통해서 확정계약과 실비정산보수가산방식에 적합한 NOS 적용 방안을 제시하였다.

Keywords

References

  1. Lee, U. S. (2000), "Management of Schedule and Cost Integration", Construction Industry Training Institute, pp 309-337
  2. Kim, J. J. (2003) "A Study on The Issues of Domestic Earned Value Payment Established In Accordance With The EVMS Introduction and Costs Associated With Its Improvement - Evaluation", Journal of Korean Society of Civil Engineers, pp 643-648
  3. Kang, I. S. (2003), "Contract Type Analysis and Improvement of Local Government Order Construction ", Journal of Korean Society of Civil Engineers, Conference Proceeding
  4. Park, H. T. (2013), "Construction Schedule Management", Gimundang Publisher, pp 11-338
  5. Park, H. T. (2014), "A Conceptual Model for Automated Cost Estimating Using Work Information Classification System of Apartment House" Journal of the Korea Society of Disaster Information. Vol. 10 No 1 pp 15-24 https://doi.org/10.15683/kosd.2014.10.1.015
  6. Park, C. J. (1998), "A Study on The Construction Management System of Schedule and Cost Integration", Myongji University Graduate, Doctoral Thesis, pp 1-100
  7. Paul Teicholz. (1987), "Current Needs for Cost Control System, Conference Proceeding on Project Control, ASCE, pp. 47-57
  8. Rasdorf, W. J. (1991), et al., "Cost and Schedule-Control Integration", Journal of Construction Engineering and Management, Vol. 117, No. 3