DOI QR코드

DOI QR Code

Contribution of Large-Scale PV Plants in the Respective Region of the Jeju Island to Electric Power during Summer Peak Times

제주도 지역별 대용량 태양광발전소들의 여름 피크타임 기여도 연구

  • Received : 2017.11.12
  • Accepted : 2017.11.23
  • Published : 2017.12.01

Abstract

Both the introduction of the Renewable Energy Portfolio Standard (RPS) system into the electric energy market in 2012 and a decrease in the cost of constructing photovoltaic (PV) power plants have been increasing the number of MW PV plants in South Korea. Jeju Island is located at the center of three nations, South Korea, China and Japan, and its provincial government declared in 2012 that the island will be a clean region where greenhouse gases are not emitted by 2030. The Jeju provincial government is now doing its best to install PV plants and wind farms to realize a carbon-free island. In this study we investigated contribution of MW PV plants to the power of the electric grid during summer peak times on Jeju Island. Mt. Halla the highest mountain in South Korea, is located at the center of Jeju Island, and we divided the island into four regions and carried out analyses of a total of 24 PV plants. The average contribution of the PV plants in the respective region to electric power of Jeju Island during summer peak times was investigated and compared with those of the other regions. The best average contribution during the 12.5% maximum load period was obtained from the PV plants in the western region, and the value was 33% during 2015 and 2016.

Keywords

References

  1. The Ministry of Trade, Industry and Energy, Republic of Korea, "Managing and Operating Guidelines on Renewable Portfolio Standard(RPS)," June 2012
  2. The Jeju Special Self-Governing Province, "Plan for Carbon-Free Island, Jeju," by 2030, 2012
  3. Egon Ortjohann & Osama A. Omari, "Peak load shaving in conventional electrical grids by small photovoltaic systems in sunny regions," IEEE, pp.1635-1637, 2002.
  4. Micheal Keesee, Jeff Newmiller & Chuck Whitaker, "Impact of distributed solar on SMUD's peak load and local distribution system," IEEE, 2008.
  5. Gae-myoung Lee and Choong-gu Hwang, "Analysis of the Generation Characteristics of the 1MW PV Plant on Jeju Island," The Transaction of the Korean Institute of Electrical Engineers, Vol. 64, No. 5, pp. 661-666, May 2015. https://doi.org/10.5370/KIEE.2015.64.5.661
  6. Gae-myoung Lee, Su-hyun Kim, Jae-hoo Yang, Se-ra Park, Su-wan Kim and Choong-gu Hwang, "Contributiveness of a Solar Power Plant to Electric Power at Summer Peak Time," Proceedings of Autumn Conference of Research Group on Smart Grid, the Korean Institute of Electrical Engineers, pp. 20-23, 2015
  7. The Korean Meteorological Administration, Weather observation data, http://www.kma.go.kr/weather/observation/past_cal.jsp.
  8. Korea Power Exchange, public access data, http://www.kpx.or.kr/www/contents.do?key.
  9. Minseung Yang & Sungmoo Lee, "Reliability Assessment of Renewable Energy," The Korean Society for New and Renewable Energy Spring Conference, pp. 339-342, 2006