신한옥형 공공건축물 실증구축사업의 작업진도 분석 및 공정개선 방안 - 신한옥형 공공건축물 실증구축 현장 3개를 중심으로 -

  • Received : 2017.06.08
  • Accepted : 2017.06.27
  • Published : 2017.06.30

Abstract

Purpose: The construction of New Han-ok style public buildings is a construction that can not be seen in traditional Han-ok, and it is a construction that combines traditional wooden structure, RC structure, and steel structure. Therefore, construction different from general construction is complicated and complex. It is necessary to accurately understand the construction method of each field rather than the general construction management method and study the method suitable for New Han-ok style public buildings. Also, since the New Han-ok style public building business is the first business to be introduced in Korea, new process management is needed rather than general process management. Method: The research method is as follows. Analyze process management through theoretical considerations and analyze the differences from general construction projects. Next, we want to identify the characteristics and problems of the process control method applied to real cases. Finally, the results of this analysis suggest ways to improve process management. Result: Therefore, it is necessary to establish a precise plan from the basic design to the construction of the public building construction management. In addition, careful planning should be made so that the supply and demand of materials and the supply and demand of personnel can be achieved smoothly.

Keywords

References

  1. 서정승, "신한옥형 공공건축물의 공정관리 개선방안에 관한 연구", 대진대학교 대학원, 석사학위 논문, 2016.6 //(Seo Jung-Seung, "A Study on the improvement method of process management on new Han-ok style Public Building project", Daejin University, 2016.6)
  2. 박창민, "건축공사의 공정계획 효율화 방안에 관한 연구", 중앙대학교 건설대학원, 석사학위 논문, 1995.6 //(Park Chang-Min, "Study on the efficient construction planning for the building projects", Chungang University, 1995.6)
  3. 김광섭, "국내 대형 공공 공사 공정관리의 문제점 분석 및 개선방안에 관한 연구", 연세대학교 석사학위논문, 1999 //(Kim Gwang0Seok, "Study on Analyzing Problems and Suggesting the Solution in field of Schedule Management in the Large Scale Public Construction Project", Yonsei University, 1999)
  4. 이석조, "부진공정 현장 관리기법에 관한 연구", 한양대학교, 석사학위논문, 2013 //(Lee Seok-Jo, "Study on the Management Methods for Behind Schedule in Construction", Hanyang University, 2013)
  5. 정천균, "한옥의 현대화에 따른 자재 및 시공방법의 문제점 및 개선방향", 중앙대학교 건설대학원, 석사학위논문, 2015 //(Jeong Cheon-Gyun, "Problems and Improvements of Materials and Construction Method in the Modernization of Hanok, a Korean Traditional House", Chungang University, 2015)
  6. 박준영 외 4인, "신한옥형 공공건축물 모델 개발 방향에 관한 연구", 대한건축학회 학술발표대회논문집, 2014. 10, No.35 Vol.2, pp. 115-116 //(Park Jun-Young, "A Study on the Model Development Direction for New Hanok Style Public Building", Conference Journal No.35 Vol.1, pp. 85-86, 2014.10)
  7. 정경윤 외 3인, "신한옥형 공공건축물 활성화를 위한 제도 개선 방향 연구", 대한건축학회 학술발표대회논문집, 2014. 10, No.35 Vol.1, pp. 85-86 //(Jeong Gyeong-Yun, "A Study on the Improvement of institution for the vitalization of New Hanok Style Public Buildings", Conference Journal No.35 Vol.1, pp. 85-86, 2014.10)