A Study on the Installation Readiness Management Method of Offshore Plant using CAD Information

CAD 정보를 활용한 해양 배관재 설치 준비율 관리 방법에 관한 연구

  • Park, JungGoo (Ship & Offshore Research Institute, Samsung Heavy Industries) ;
  • Kim, HoJung (Ship & Offshore Research Institute, Samsung Heavy Industries) ;
  • Kim, MinGyu (Ship & Offshore Research Institute, Samsung Heavy Industries) ;
  • Park, JiChan (Ship & Offshore Research Institute, Samsung Heavy Industries)
  • 박중구 (삼성중공업(주) 조선해양연구소) ;
  • 김호정 (삼성중공업(주) 조선해양연구소) ;
  • 김민규 (삼성중공업(주) 조선해양연구소) ;
  • 박지찬 (삼성중공업(주) 조선해양연구소)
  • Received : 2018.10.09
  • Accepted : 2018.11.28
  • Published : 2019.04.20

Abstract

In this study, we propose a piping material supply management method using CAD system. The piping materials installed in super large offshore plants have very complicated connection conditions. Therefore, it is very difficult to determine the order of receipt of a large number of installation materials. Therefore, we have developed a system that can automatically check the preparation rate of installation materials prior to the installation process. We have developed an algorithm to obtain connection information among installation items from PDMS system. We have developed an algorithm that can determine the order of installation materials to be installed using the connection information. The order of the installation material is determined by taking into account the constraint conditions for the complete installation of the piping material. We confirm the effectiveness of the developed algorithms in the operating system. This system is also used to manage installation schedules and plan the installation manpower.

Keywords

References

  1. Back, M.G., Woo, J.H., Lee, P. & Shin, J.G., 2016. Productivity improvement strategies using in simulation offshore plant construction. Journal of Ship Production and Design, 32(3), pp.25-33.
  2. Ham, D.G., Back, M.G., Park, J.G. & Woo, J.H., 2016. A study of piping leadtime forecast in offshore plants outfitting procurement management. Journal of the Society of Naval Architects of Korea, 53(1), pp.29-36. https://doi.org/10.3744/SNAK.2016.53.1.29
  3. Lee, H.S., 2013. A case study on improvement of pipe outfitting production process using TOC. Master's Thesis. Ulsan: University of Ulsan.
  4. Park, J.G., et al., 2018. A study on piping material management for offshore plant pipe fabrication. Proceedings of The Korean Institute of Industrial Engineers, 2018(4), pp.1042.
  5. Park, J.G. & Woo, J.H., 2018. A study on process management method of offshore plant piping material. Journal of the Society of Naval Architects of Korea, 55(2), pp.124-135. https://doi.org/10.3744/SNAK.2018.55.2.124