Integrated Project Delivery in the Pre-construction Phase : Case Study of IPD for Lean Construction

사례 연구를 통한 Pre-con 단계의 린 건설 기반 IPD 프로젝트 적용 방안 도출

  • Jang, Hanbyeol (Department of Architectural system Engineering, Hanyang University) ;
  • Lee, Joosung (Department of Architectural Engineering, Hanyang University) ;
  • Ahn, Yonghan (Department of Architectural Engineering, Hanyang University)
  • Received : 2019.07.09
  • Accepted : 2019.08.23
  • Published : 2019.11.30

Abstract

Current construction project processes pose difficulties for construction management as inefficient communication between project participants seldom accurately reflects the needs of the owner. To solve this problem, lean construction-based Integrated Project Delivery (IPD), which facilitates cooperation and builds trust through the formation of horizontal relationships among participants, is becoming increasingly popular. However, although lean construction-based IPD improves productivity in the construction industry, few studies have focused specifically on developing effective methods that maximize the benefits gained from lean construction-based IPD. This study therefore analyzed success factors for lean construction-based IPD projects by analyzing prior studies to identify factors that support IPD success. Application methods were analyzed and an example of how they are actually used in the field was examined through an in-depth single case analysis. The findings of this research can be applied to support lean construction-based IPD projects in Korea, improving their efficiency and boosting owner satisfaction.

현재의 건설사업 과정은 사업 참여자들 간의 비효율적인 의사소통이 소유자의 요구를 정확히 반영하지 못하기 때문에 효율적인 건설관리가 어려운 상황이다. 이를 해결하기 위해 최근 참가자들 간의 수평적 관계 형성을 통해 협력과 신뢰구축을 가능하게 하는 린 건설기반 통합 프로젝트 발주방식이 적용되고 있다. 린 건설 기반의 IPD는 건설 산업의 생산성 향상에 효과적임에도 불구하고, 기존 연구에서는 린 건설 기반의 IPD 를 적용하는 구체적인 방법이 부족하다. 본 연구는 린 건설 기반의 IPD 프로젝트가 어떻게 성공했는지 분석했다. 이 연구는 IPD 프로젝트가 성공으로 이어질 수 있는 영향 요인을 도출하기 위해 먼저 기존 연구와 보고서를 통해 분석되었다. 영향 요인을 기반으로 단일 사례 분석을 통해 실제 적용 방법을 분석하였다. 연구의 범위는 이전의 분석을 바탕으로 IPD 프로젝트의 각 성공요인에 대한 적용 방법을 제시하는 것으로 제한되었다. 본 연구는 향후 국내 건설 기반 IPD 프로젝트의 실행에 사용될 수 있다.

Keywords

References

  1. Abdelhamid, T.S. (2012). All about Lean construction, Construction Employer Associated Builders exchange magazine.
  2. AIA National. (2007). "Integrated project delivery: A Guide." AIA California Council.
  3. AIA National. (2012). "IPD case studies." AIA California Council.
  4. Ashley, D.B., Lurie, C.S., and Jaselskis, E.J. (1987). "Determinants of construction project success." Project Management Journal, 18(2), pp. 69-79.
  5. Briscoe, G., and Andrew, D. (2005). "Construction supply chain integration: an elusive goal?" Supply Chain Management: An International Journal, 10(4), pp. 319-326. https://doi.org/10.1108/13598540510612794
  6. Center for Innovation in the Design & Construction Industry (CIDCI). (2018). "Integrated project delivery: An action guide for leaders." CIDCI.
  7. Colin, R. (2002). Real World Research. 2nd ed, Blackwell Publishers, pp. 220-223.
  8. ConsensusDocs. Standard multi-party integrated project delivery (IPD) agreement. ConsensusDocs.
  9. Darrington, J. (2011). "Using a design-build contract for Lean Integrated Project Delivery." Lean Construction Journal, pp. 85-91.
  10. Eriksson, P.E. (2010). "Improving construction supply chain collaboration and performance: A lean construction pilot project." Supply Chain Management: An International Journal, 15(5), pp. 394-403. https://doi.org/10.1108/13598541011068323
  11. Ghassemi, R., and Becerik-Gerber, B. (2011). "Transitioning to Integrated Project Delivery: Potential barriers and lessons learned." Lean Construction Journal, pp. 32-52.
  12. Han, J.H. (2009). "A study on constraint analysis connected with lean construction." MS thesis, Donga University.
  13. Jang, M.W. (2012). "A Study on the Derivation of Priorty Item for IPD Adoption in Domestic Construction Indurstry." MS thesis, Yeungnam University.
  14. Jeon, H.W., Ahn, J.H., and Park, H.S. (2011). "A Basic Study on Design Process of BIM for the Use of LEAN and IPD Methods in Domestic Industry." Korean Journal of Construction Engineering and Management, KICEM, 31(1), pp. 71-72.
  15. Kang, K.H., Park, J.R., Kim, J.H., and Kim, J.J. (2010). "A Study on the Introduction of IPD by the Study of Cases in the U.S." Journal of the Architectural Institute of Korea Structure & Construction, 30(1), pp. 317-318.
  16. Kim, D.Y. (2003). "Guidelines for Implementing Lean Construction." Journal of the Architectural Institute of Korea Structure & Construction, 19(9), pp. 121-128.
  17. Kim, S.W. (2009). "The Public Project Application of Management Analysis and Management Plan Proposed Based on Lean for Government Owner." MS thesis, Kyungnam University.
  18. Kim, Y.W., and Kim, K.H. (2008). "A Study on Preconstruction Process in Support of Lean Project Delivery System : Case Study of Children's Hospital at Bellevue, Wa, U.S.A." Korea Institute of Healthcare Architecture, pp. 47-54.
  19. Kim, Y.J., Lee, Y.M., Shin, T.H., Kim, Y.S., and Chin, S.Y. (2009). "A Preliminary Study for Adoption of IPD to Public Sector Delivery Systems in the Korean Construction Industry." Journal of the Architectural Institute of Korea Structure & Construction, 29(1), pp. 609-612.
  20. Koo, B.S., Park, H.S., Chang, C.K., and Kim, D.Y. (2006). "Implementation of Lean Construction on London Heathrow Airport's T5 Project." Journal of the Architectural Institute of Korea Structure & Construction, 22(7), pp. 141-148.
  21. KPMG. (2013). "Integrated Project Delivery: Managing risk and making it work for all parties."
  22. Lean Construction Institute. (2018). "GREAT DESIGN ENABLED BY LEAN"
  23. Liu, M., Griffis, F.H., and Bates, A.J. (2013). "Compensation Structure and Contingency Allocation in Integrated Project Delivery." American Society for Engineering Education conference & exposition.
  24. Mesa, H.A., Moleanaar, K.R., and Alarcon, L.F. (2019). "Comparative analysis between integrated project delivery and lean project delivery." International Journal of Project Management, 37, pp. 395-409. https://doi.org/10.1016/j.ijproman.2019.01.012
  25. Sarhan, S. (2015). "The Concept of Waste as Understood in Lean Construction." Lean Construction Blog.
  26. Song, K.S., Yun, J.S., and Kwon, O.C. (2011). "A Case Analysis on the Multi-Party Contract of IPD for the BIM Acquisition Process." Journal of the Architectural Institute of Korea Structure & Construction, 31(2), pp. 445-446.
  27. Song, S.M., Kim, Y.S., Chin, S.Y., and Kwon, S.W. (2011). "An Analysis on the Perception of Domestic Construction Engineer to Introduce IPD." Korean Journal of Construction Engineering and Management, KICEM, 2(2), pp. 72-80.
  28. Song, W.S., Jung, S.H., Lee, K.S., Song, Y.W., and Choi, Y.K. (2013). "Research on the Implementation of IPD for Customized Design Project Design Change." Journal of the Architectural Institute of Korea, 33(1), pp. 579-580.
  29. Shin, K.C., and Ham, I.H. (2012). "A Study of Integrated Project Delivery (IPD) Methods Based on Building Information Modeling (BIM)." Journal of the Korean Digital Architecture Interior Association, 12(3), pp. 15-25.
  30. University Of Minnesota. (2016). "Motivation and Means: How and why IPD and Lean lead to success." Integrated Project Delivery Alliance, Lean Construction Institute.
  31. Wills, B. (2014) "The Advantage and Limitation of Single Case Study Analysis." E-international relations students.