• Title/Summary/Keyword: Contract Amount Adjustment System

Search Result 8, Processing Time 0.033 seconds

Improvement on the Managerial Method of Price Fluctuation System (물가변동제도 운영방식 개선방안)

  • Lee, Jae-Seob;Shin, Young-Chul
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.2
    • /
    • pp.3-11
    • /
    • 2011
  • There are several causes to recalculate the contract amount in public construction projects. Among them, the escalation clause was introduced in 1969 and now the condition to recalculate the cost is effective after 90 days from the date of contract and the rate of fluctuation should be more than 3% from the date of bidding. The two calculation methods for the rate of fluctuation are item-adjustment and index-adjustment. According to the results of investigation into 4 public institutions and 163 projects, all of them have used the method of index-adjustment and the rate of projects that spend over 6 months obtaining the approval of contract amount adjustment is more than 90%. The reason for spending lots of time is caused by problems of the calculation method on the price fluctuation rate. Therefore, it is necessary that the calculation method should be diversified to cope with the problems and a option of the builder should be expanded as well. Furthermore, if the way to apply correction factors to construction price index and average index based on the producer and consumer price index made by the bank of Korea is added, then the duration will be reduced without additional expenses. This study proposed the diversification of the calculation method using price fluctuation rate and builders' expanded options as improvement on the managerial method of Price Fluctuation System for the prompt and efficient contract amount adjustment.

A Study on Improvement of Contract Regulations for Adjusting Contract Amount in Public Construction - Focused on examples of price fluctuation classification - (공공건설 계약금액 조정의 계약예규 개선방안 연구 - 물가변동 분류 사례 중심으로 -)

  • Lee, Wonjei;Shin, Manjoong
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.4
    • /
    • pp.82-89
    • /
    • 2020
  • Article 64 of the Enforcement Decree of the National Contract Act The requirement of the pre-amendment statute related to the adjustment of the contract price was 5% or more of the price fluctuation rate from the date of the contract. However, the meeting requirement was changed from 5% or more to 3% or more from the date of signing of the Presidential Decree No. 19035 to 2005. 9. 8. The method of adjusting the contract amount was also changed to determine the contractor's desired adjustment method at the time of contract. Alleviating these requirements and revising the empowerment of contract partners is intended to prevent difficulties in achieving smooth objectives by applying to public construction contractors without unfairly benefiting or unfavorable to contract partners. Even if the standards are relaxed and the rights are secured as described above, if the existing provisions for the adjustment of price fluctuation are applied, unlike the original purpose of the government system, the Korea Bank's price economic statistics classification method and the contract construction classification criteria applied in public construction work Due to the inconsistency, it can be seen that the amount of adjustment for price fluctuation by construction type is excessive and underestimated. Therefore, the purpose of this study is to analyze problems through cases and to make appropriate construction cost adjustment through improvement measures.

A Basic Study on Effective Adjustment Method for Construction Escalation/De-Escalation Price (건설공사 중 물가변동에 따른 효율적인 계약금액 조정에 관한 기초 연구)

  • Sung, Ju-yong;Kim, Dong-jin;Lee, Min-jae
    • Korean Journal of Construction Engineering and Management
    • /
    • v.20 no.3
    • /
    • pp.3-11
    • /
    • 2019
  • The construction of a facility is an act whereby infrastructure such as roads and railways and other facilities such as housing and office spaces are constructed, and due to the characteristics of the relevant industry where such construction is carried out in a custom order method, it requires a long period of time mostly. While the construction is carried out over a long period of time, fluctuations in the price of raw materials required for the construction occur. Therefore, the cost of the construction also fluctuates inevitably. The fluctuation of the construction cost meshes closely with the profit of a constructor and the efficiency of government spending. Therefore, it is necessary to maintain the construction cost at a reasonable level by adjusting the construction cost rationally in order to secure the required construction quality and spend the budget efficiently. The buffer system for solving such problem is the contract amount adjustment system by fluctuations in prices (Escalation/De-Escalation). In this study, the method combining the escalation method based on the item adjustment method was suggested for an efficient contract amount adjustment method. In addition, it is proposed that there be an investigation and codification of matters not applied to government acts and regulations on contracts related to the adjustment of fluctuations in prices legally.

A Delphi Study on the Price Escalation Clause in a Construction Contract

  • Choi, Min Soo;Kim, Moo Han
    • Architectural research
    • /
    • v.8 no.1
    • /
    • pp.69-76
    • /
    • 2006
  • The purpose of this study is to suggest policies to improve the price escalation system in a construction contract through a Policy Delphi technique. The Delphi, including two times questionnaires and a group discussion, was conducted by joining 14 experts. Also, the escalation provisions of various countries were examined. Results of the Delphi showed that the minimum fluctuation rate for price escalation was desirable at a level of 3%. To compute the fluctuation rate, calculating the price fluctuation of overall articles was more desirable than using price indices. A bidding date was more reasonable as the initial date of change in price. Losses caused by price change should be shared between contractor and owner; therefore a deduction rate should be introduced in price escalation. Meanwhile, overhead and profit should be adjusted in proportion to the fluctuation rate; but advance payment or the delayed construction amount should be deducted from the adjusted amount.

Analysis of Road Construction Projects' Escalation under Historical Data-Based Estimate System in Jeju (실적공사비가 적용된 제주도 도로공사의 물가변동률 영향 분석)

  • Hong, Jeong-Ho;Lee, Dong Wook
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.34 no.2
    • /
    • pp.667-676
    • /
    • 2014
  • This study has conducted case studies in order to suggest alternatives to the historical data-based estimate system. Price fluctuation calculation methods based on historial cost indexes, standard estimate and construction cost indexes were applied to 9 road construction sites in Jeju for an analysis. As a result, in 5 construction sites (about 56% of 9 sites), the index control rate calculated based upon historical data-based estimate system was higher than that calculated based upon standard estimate and construction cost indexes. Thus the establishment of the requirements for the adjustment of contract price due to price fluctuation delays, which leads to a significant difference in price fluctuation amount. And, in an analysis of construction cost indexes, the indexes for road construction were used for calculating index control rate which ranges from 2.0 to 9.4 percent, indicating the time of construction amount and price fluctuation application has a significant influence on index control rate.

A study on the relationship between cost fluctuation and cost elements -focused on defense R&D project- (원가변동과 원가 비목 간 영향력에 관한 연구 -국방연구개발사업을 중심으로-)

  • Kang, Kyung-Mok
    • Journal of the Korea Convergence Society
    • /
    • v.9 no.3
    • /
    • pp.223-230
    • /
    • 2018
  • This study analyzes the cost fluctuation between cost in contract stage and cost in adjustment stage in defense R&D project. This research shows that certain costs hold with the cost fluctuation and their degree of influence. The results of first analysis show that 13 out of 17 costs have a relationship with the cost fluctuation. The estimate of direct labor cost is positive and significant at the 0.1% level(direct labor = 1.022, t = 38.355). The estimate of amount of cost paid to subcontractor is positive and significant at the 1% level(amount paid to subcontractor = 0.942, t = 51.894). The results of second analysis show that all the direct costs have a relationship with the cost fluctuation(The fact that cost system is focused on direct labor cost is a consideration in this analysis). The estimate of direct labor cost is positive and significant at the 0.1% level(direct labor = 2.014, t = 21.787). The estimate of amount of cost paid to subcontractor is positive and significant at the 0.1% level(amount of cost paid to subcontractor = 1.068, t = 15.636). This finding supports a proposal theory that cost system is focused on direct labor cost through actual proof analysis and an inducement that amount of cost paid to subcontractor is a way to reduce the R&D cost.

Development of a Cost Index for Site Developing Project (단지조성공사용 공사비 지수의 개발)

  • Bae Keon;Lee Tai-Sik;Park Jong-Hyun;Lee Won-Yong
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.423-426
    • /
    • 2002
  • The foundation for developing a cost estimation system based on historical data has been being prepared in Korea. Historical data is a priori of developing a cost estimation model. Cost Index, one of the historical data, is used to estimate construction cost and to adjust the amount of contract money in the foreign country, whereas it is not used in domestic except for the road construction project in Korea. Construction cost indices can be used by an estimator in tender analysis, pricing, price adjustment, cost planning, and forecasting. In this regards, this paper identified the problems in developing Cost Index evaluation process by comparing the standard of framing Cost Index used in British to the one used in Korea. Then, the scheme for improving a Cost Index required for Site Developing Construction was proposed. Twenty-two cases of engineering estimate data were used to compare the domestic standard to the foreign one in deriving a Cost Index.

  • PDF

Orders Status Analysis on the Successful Bidder Decision Method of Turnkey Alternative Tendering Construction (턴키·대안입찰공사 낙찰자 결정방식에 의한 수주현황 분석)

  • Park, Hong-Tae;Lee, Yang-Kyu
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.33 no.2
    • /
    • pp.771-780
    • /
    • 2013
  • Inspection system which was performed in the past selected the final winning bidder by separating Pre-Qualification, the basic design evaluation and price evaluation. However, turnkey and alternative bidding construction has selected way to determine the successful bidder as the best design and the most low cost method, comprehensive evaluation method (bid price adjustment, design score adjustments, weights standard), the best design and the fixed amount method from january 1, 2010 to the present. Due to these institutional problems, orders institutions were often a way to determine the successful bidder to apply differently for identical or similar construction. Therefore this study winning bidder selection criteria through analysis of construction the number and construction order performance, order performance by work division and institutional orders, the weights bidder order performance and orders status of turnkey alternative tendering construction to civil part performed in domestic.