Comparative Analysis of Conventional Tact and Compositive Tact in Apartment House Finishing Construction (공동주택 마감공사의 기존 Tact와 복합병행 Tact 비교분석 - 공동주택 미장공사 중심으로 -)

  • Hwang, SuHyeon;Sim, JeaHyung;Ham, NamHyuk;Kim, JaeJun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.23 no.4
    • /
    • pp.47-56
    • /
    • 2022
  • In a construction project, process planning is an important factor in determining the success or failure of a project. In particular, it is necessary to systematically establish a process plan in the early stage because the finishing work of an apartment house involves more interference than the foundation work or the frame work. First, in this study the problems of Tact process management were identified, Based on the data from the case project, conventional Tact process management and compositive Tact process management were compared and analyzed. Second, cost analysis was performed on applicable plastering work to suggest the necessity and direction of compositive Tact process management. Third, the appropriateness of manpower according to the number of construction households is analyzed through cost analysis. Through this, the validity and effectiveness of compositive Tact process management were verified based on the results derived from this study.

IMPROVEMENT OF TACT SCHEDULE MANAGEMENT PROCESS FOR THE FINISH WORK OF APARTMENT HOUSES

  • Joo-Young Jung;Sang-Ho Yoon;Kyung-Kook Lee;Chang-Gyo Kim;Jae-Youl Chun
    • International conference on construction engineering and project management
    • /
    • 2007.03a
    • /
    • pp.554-562
    • /
    • 2007
  • This study determined tact process paths by separating the finish works according to the properties of work areas and work relations in order to apply the tact schedule management to the finish works. In addition, by suggesting preparing and sharing the workflow charts, the experiments can be shared between the executors and any possible frictions between the specialist works can be identified in advance. In addition, any errors on the plan can be reviewed and modified through the measurement stage of tact plan attainment rate. The process of tact schedule management is improved with such tools and methods and the efficiency of the process through the application of cases was verified.

  • PDF

The application of tact time at finish work for building construction - Focused on Office Building - (건축마감공사에서의 택트타임 설정을 통한 작업조정 프로세스 개발 - 오피스 건축물을 중심으로-)

  • Yoon, You-Sang;Suh, Sang-Wook
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.6 s.28
    • /
    • pp.90-97
    • /
    • 2005
  • Poor usage of work-continuity for planning and management is one of the leading causes of decreased productivity in high-rise and complexity construction projects. For efficient finish work, tact scheduling method needs to be implemented according to tact time. But there are the studies about zoning of work area, daily construction information and tact planning and management, there are not the studies about tact time yet. The purpose of this study is to help implementation of tact scheduling by tact time and adjusted work-plan. The main contents of this study are as follow; (1)Tact time has been calculated as coordination of work-plan between a general contractor and specialties. (2)Project-plan can be without delay by tact time calculation method.

Development and Application of TACT Management System (TACT 공정관리 시스템 개발 및 적용 사례)

  • Suh Sang-Wook;Kim Jae-Ho;Kim Sun-Kuk;Kim Chang-Duk;Lee Hyun-Soo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.4 no.4 s.16
    • /
    • pp.145-154
    • /
    • 2003
  • The change in environment of construction industry and the advancement of information technology require the improvement of construction project efficiency. However, construction industry still lacks performance-measuring tools that are the requirements of efficient project management system. In case of the schedule management system, schedule is usually being managed by result-oriented measurements such as completion time, spent cost, and progress rate, which are not good enough to control the overall continuity of work-flow. This research aimed to systemize the overall construction process and to develop the indicators for measuring performance of TACT activities during finishing work period that can contribute to the systemization of TACT management.

Development and Application of TACT Management System (TACT 공정관리 시스템 개발 및 적용 사례)

  • Kim Jea-Ho;Suh Sang-Wook;Kim Sun-Kuk;Kim Chang-Duk;Lee Hyun-Soo
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.126-134
    • /
    • 2003
  • The change in environment of construction industry and the advancement of information technology require the improvement of construction project efficiency. However, construction industry still lacks performance-measuring tools that are the requirements of efficient project management system. In case of the schedule management system, schedule is usually being managed by result-oriented measurements such as completion time, spent cost, and progress rate, which are not good enough to control the overall continuity of work-flow. This research aimed to systemize the overall construction process and to develop the indicators for measuring performance of TACT activities during finishing work period that can contribute to the systemization of TACT management.

  • PDF

Reengineering of TACT Process Management Analyzed on Task Information (업무정보 분석을 통한 TACT공정관리 프로세스 재설계)

  • Kim, Ok-Kyue;Park, Jun-Mo;Kim, Beop-Su
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.5
    • /
    • pp.113-124
    • /
    • 2012
  • TACT process reengineering is applied to the finish work of apartment buildings and extra tall buildings to conduct efficient process control in Korea. Non-systemized information on the performances, however, causes difficulties in building a database for such records and it takes long time to find the relevant information. In order to solve such problems, scientific and quantitative understanding on the construction information and data is required to perform TACT process reengineering satisfactorily and also proper management plan should be provided for the working level staff to understand the required information and data more easily. In this regard, this paper reorganizes the TACT process reengineering based on the general process control and classifies the items of required information to redesign. Redesigned process was verified by specialists making use of work-information matrix. As a result, paper contributed to increasing comprehension level of the working level people and when the persons in charge are transferred to other duty, it makes them understand all the working procedure faster, which enables the departments involved to carry out their cooperation and adjustment more efficiently.

TACT Scheduling & Monitoring of Apartment Finish Works based on the BDM Technique (BDM기법을 적용한 공동주택 마감공사 TACT공정계획 수립 및 운영)

  • Kim, Seon-Gyoo;Yoo, Jae-Woo;Kim, Dong-Sub;Park, Jong-Il
    • Korean Journal of Construction Engineering and Management
    • /
    • v.15 no.2
    • /
    • pp.3-11
    • /
    • 2014
  • As the recent construction projects have been carried out as a mixed-use complex project that includes architecture, civil, mechanical, electrical, and landscape, as well as become bigger and high-rise with the increased repetitive works, the TACT technique has received more attention as an effective method for achieving a target completion date by securing the continuous works. Although the TACT technique can maintain a steady flow without the interruption of works in order to utilize the resources of the repetitive works, it can not be considered as the systematic scheduling technique because the schedule computations are not possible as well as a critical path can not be recognized. This paper proposes the applicabilities of scheduling and monitoring the TACT schedule by the BDM technique as comparing and analyzing the methodologies for apartment finish works by the Excel, the Primavera(P6) based on the PDM technique, and the Beeliner based on the BDM technique that is a new networking technique, respectively.

Understanding and Implementation Strategy of Tact Time, Pitch Time and Cycle Time (택트타임, 피치타임, 사이클타임의 이해와 적용방안)

  • Choe, Seong-Un
    • Proceedings of the Safety Management and Science Conference
    • /
    • 2011.11a
    • /
    • pp.557-561
    • /
    • 2011
  • The study proposes three types of production lead time according to the production or demand pattern. First of all, it discusses the difference of three lead times. While pitch time and cycle time are used in push system with process stock and mass conveyor production, the tact time is used in pull system like as JIT based lean production system.

  • PDF

TACT Productivity Management for Finish Works of Residential Buildings using Productivity Achievement Ratio (PAR) (공동주택 마감공사 TACT 기법 생산성 관리 - Productivity Achievement Ratio를 활용한 생산성 관리 -)

  • Joo, Seonu;Park, Moonseo;Lee, Hyun-Soo;Lee, Kwang-Pyo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.3
    • /
    • pp.36-48
    • /
    • 2015
  • To complete various types of finish works with higher quality in much less time, TACT, which was mostly used for high-rise buildings, has been adapted to meet the needs for systematic schedule management in construction sites. However, the effectiveness of adapting TACT has not been shown as expected due to the different perspectives on productivity from both general contractor and subcontractors based on unforeseen conditions according to the types of site. Furthermore, not enough theoretical backgrounds, empirical data, and systematic approaches to solve the fundamental problems caused by each participants' different views on productivity has produced obstacles for establishing effective solutions. Therefore, this research aims to analyze the possible main reasons for having different point of views regarding productivity among various participants of residential building sites using TACT based on literature review, site survey, and interviews. Also, case study was conducted to propose obtainable productivity (OP) regression equation and productivity achievement ratio (PAR) with reduction factors (RFs) and actual productivity (AP) data from an actual construction site. The proposed outcome may assist general contractors converting output management with PPC to productivity management with actual data using PAR. On the other hand, subcontractors would be able to estimate theory-based maximum productivity of construction sites with TACT by using OP. The PAR will enhance the communication between general and sub-contractors for their decision making process. Finally, the main RFs derived from PAR could be used as essential keys for productivity management to increase the economical and operational effectiveness of the construction project.

TACT Modification Methods for Responding to Delay in Winter Season (동절기 공정지연 대응을 위한 TACT 공정 조정방안)

  • Kim, Dae-Kyu;Jeong, Yong-Joon;Lee, Jun-Ho;Moon, Hyun-Seok;Koo, Kyo-Jin;Hyun, Chang-Taek
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2011.11a
    • /
    • pp.125-126
    • /
    • 2011
  • Construction projects are being more complicated in proportion to the economic development. Process management is a critical issue in the construction that decides success of a project. Especially, a TACT method which divides and manages resources to repeat each activity is more important. Although becoming an issue dealing with the delay at winter season, it is not property developed. This paper suggests 'activity priority method' and 'TACT unit method' through case study. We validate necessity and efficiency of the TACT method through simulations and a survey. We expect cost reduction by decreasing unnecessary spending.