Design of the Boiler Load Distribution System

보일러 본체 지지장치 하중교정 시스템 설계

  • Published : 2000.07.17

Abstract

Due to the long time operation of the thermal power plant boiler. the load redistribution of the sling rods is occurred. To enlarge the sincerity of the boiler. measuring and adjusting the actual load of the sung rods is required. The original targets were reached from the 1-year-study. Survey related to the load distribution system for the boiler, systematic design of the hydraulic unit and hydro cylinder, detailed design of the hydraulic unit and hydro cylinder.

Keywords