An Assessment of Field Application of Elementary Technology for Reducing Construction Duration in the Apartment Housing Construction

공동주택 골조공기단축을 위한 요소기술의 현장 적용성 평가

  • 김규회 (서울대학교 대학원 건축학과) ;
  • 박문서 (서울대학교 건축학과) ;
  • 이현수 (서울대학교 건축학과) ;
  • 박송우 (서울대학교 대학원 건축학과) ;
  • 주선우 (서울대학교 대학원 건축학과)
  • Published : 2007.11.09

Abstract

Recently, construction companies prefer to use large scale system forms to prepare for lacking of skilled workers, aging and the chances of application of pre-build&post-sale policy. In result of the effort and interest, the duration for framework of domestic high rise buildings has been accomplished to 3-4days per floor but for the apartment housing which form over 90% of the domestic construction industry, and especially the middle story RC apartments which is the main part, the duration for framework is only about 6-8days per level. This is only about 50% of the duration per level of RC residential buildings in North America. In previous researches elementary technology, which has potential of duration reduction, was proposed and this research suggest the applicability in construction sites and ways to improve it using elementary technology applied Mock-up Test. Furthermore, we analyze the productivity and T/C usage rate of the 6day-Cycle and suggest an improved model.

최근 건설 회사들은 기능 인력의 부족현상과 고령화 현상, 그리고 선 시공 후 분양 제도의 도입 가능성 등에 대비하기 위하여 대형 시스템 거푸집의 사용을 선호하고 있다. 이러한 관심과 노력의 결과로 국내 초고층 건축의 경우는 층당 3-4일의 골조공기를 달성하고 있으나, 우리나라 건설사업의 90%이상을 차지하고 있는 공동주택, 그 중 대부분을 차지하고 있는 중층 RC조 아파트의 경우는 6-8일 정도의 층당골조공기를 형성하고 있다. 이는 북미 일반 RC조 주거건축 층당공기 대비 50%수준에 머물러 있는 실정이다. 이에 본 연구에서는 선행 연구를 통하여 도출된 공기단축의 가능성을 가진 요소기술들을 적용한 Mock-up Test를 통하여 현장적용가능성 및 개선방안을 검토하였다. 또한 기존 6day-Cycle의 단위생산성 및 T/C 가용율에 대하여 분석하고, 기존공정대비 공기단축형 공정모델의 단위생산성 및 T/C 가용율을 비교하였다.

Keywords