A Case Study of maintenance cost estimation for military official residence building in BTL project

BTL사업 군관사 건축물의 유지관리비용 산정에 관한 연구

  • Published : 2008.11.07

Abstract

The purpose of this study is to predict the maintenance cost for military official residence building projects which were ordered for five military official residence building. In conducting this study, the adapted research method was to classify initial investment for each construction of the military official residence building and to estimate maintenance cost. This study was analyzed by studying the estimation of maintenance cost in the apartments and present value analysis method. The results of this research are as follows. 1) The initial investments was analyzed that the total construction cost would be 1,683,286 thousand won ; construction(79%), civil(3%), landscaping(2%), MEP(5%), heating and hot water supply system(5%), and water supply and sanitary system(6%) per square meter. 2) Based on the result analyzed above, the maintenance cost of the apartments was analyzed and then estimated the proper maintenance cost by using maintenance cost estimation method and present a value analysis method.

본 연구는 군관사 건축물의 적정 유지관리비용의 산정을 위하여 수행하였다. 이를 위해 BTL방식으로 발주된 5개의 군관사 건축물을 사례대상으로 선정하였으며, 사례대상 건축물의 초기투자비용을 공종별로 분류한 후 장기 수선비용을 산정하였다. 또한 이렇게 산정된 공종별 장기수선비용을 공동주택 장기수선충당금 산정방법과 현가분석 산정방법을 준용하여 비교 분석하였다. 상기 같은 목적과 방법에 따라 진행된 본 연구의 결론을 요약하면 다음과 같다. 첫째, 초기투자비는 $m^2$당 건축 13,331,712원(79%), 토목 588,125원 (3%), 조경 285,658원(2%), 전기소화설비 760,549원(5%), 난방급탕설비 906,059원(5%), 급수위생설비 960,759원(6%)이며 초기투자비의 총 합계는 16,832,862천원으로 분석되었다. 둘째, 산정된 공종별 초기투자비를 바탕으로 공동주택의 장기수선비용을 산정한 후 공동주택 장기수선충당금 산정방법과 현가분석 산정방법을 각각 준용하여 적정 유지관리비용을 산정하였다.

Keywords