Preliminary Analysis of the Bid Success Ratio according to the Characteristics of Overseas Construction Projects

해외건설 프로젝트 특성에 따른 입찰 성공률 분석에 관한 기초연구

  • Kim, Seung-Won (Department of Architectural Engineering, Kwangwoon University) ;
  • Lee, Kang-Wook (Korea Research Center for Overseas Construction) ;
  • Yu, Jung-Ho (Department of Architectural Engineering, Kwangwoon University)
  • Received : 2019.01.22
  • Accepted : 2019.03.12
  • Published : 2019.05.31

Abstract

In the construction industry, bidding competitiveness is the most basic and important competence of the company. Bidding competitiveness comes from competitive advantage, but the strategy of the company to capture bidding competitiveness varies with the characteristics of the project. In particular, overseas construction is where uniqueness of the construction industry and the specificity of international business coexist. This study analyzes the bidding success ratio and the level of bidding difficulty by project characteristics with 12,952 overseas construction bidding cases. Consequently, it was found that the bidding success ratio of Middle East and North Africa (MENA) and civil engineering was the lowest in each group of project characteristics, and therefore the level of bidding difficulty is high, respectively. In addition, it was confirmed that the bidding success ratio of small size or short duration project was relatively high, and the bidding success ratio of both the negotiated bidding in the bidding method group and the private sector in the client type group was respectively high. However, Kruskal-Wallis test in contract type and period shows that there is no statistically significant difference in the bidding success ratio by group.

건설산업에 있어 입찰 경쟁력은 기업의 가장 기본적이며 중요한 역량이다. 입찰 경쟁력은 기업이 보유한 경쟁우위에 기인한 것이나, 입찰 경쟁력을 확보하기 위한 기업의 전략은 결국 프로젝트의 특성에 따라 달라질 수 있다. 특히 해외건설은 건설업의 고유성과 해외사업이라는 특수성이 공존하는 분야로, 본 연구는 국내기업들이 도급형 방식으로 실시한 12,952건의 해외 프로젝트 입찰 사례를 수집하여 프로젝트 특성에 따른 입찰 성공률을 분석하고 그 차이를 확인하여 상황별 입찰 난이도를 진단하였다. 분석 결과, 지역별로는 중동 지역에서, 공종별로는 토목 부문이 입찰 성공률이 낮아 입찰활동에 대한 난이도가 높음을 파악할 수 있었다. 또한 프로젝트 규모나 기간이 작은 그룹이 상대적으로 입찰 성공률이 높음을 확인하였고, 입찰방식에 따라서는 수의시담 방식이, 발주자 형태별로는 민간부문 발주 프로젝트의 입찰 성공률이 높은 것으로 분석됐다. 반면 계약방식이나 시대구분의 경우 Kruskal-Wallis test 결과, 그룹 간 기업별 입찰 성공률이 통계적으로 유의미한 차이가 없음을 확인하였다. 본 연구는 산업차원에서 해외건설 프로젝트 특성요인에 따른 입찰 성공률을 다각적으로 분석했을 뿐 아니라 해외건설 실무자에게 상황별 수주활동 난이도 진단 및 효과적인 입찰전략 수립을 위한 기초자료를 제공한다는 점에서 의의가 있다.

Keywords

GGRHC4_2019_v20n3_122_f0001.png 이미지

Fig. 1. Overseas construction contract value by Koreanconstruction firms (data from International Contractors Association of Korea (ICAK))

GGRHC4_2019_v20n3_122_f0002.png 이미지

Fig. 2. Overseas construction bidding value by Korean construction firms (data from ICAK)

GGRHC4_2019_v20n3_122_f0003.png 이미지

Fig. 4. BSR ranges by work type

GGRHC4_2019_v20n3_122_f0004.png 이미지

Fig. 5. BSR ranges by Project size

GGRHC4_2019_v20n3_122_f0005.png 이미지

Fig. 7. BSR ranges by bidding type

GGRHC4_2019_v20n3_122_f0006.png 이미지

Fig. 8. BSR ranges by contract type

GGRHC4_2019_v20n3_122_f0007.png 이미지

Fig. 3. BSR ranges by region

GGRHC4_2019_v20n3_122_f0008.png 이미지

Fig. 6. BSR ranges by project duration

GGRHC4_2019_v20n3_122_f0009.png 이미지

Fig. 9. BSR ranges by client type

GGRHC4_2019_v20n3_122_f0010.png 이미지

Fig. 10. BSR ranges by period

Table 1. Key Attributes of Overseas construction projects

GGRHC4_2019_v20n3_122_t0001.png 이미지

Table 2. Normality test on Bidding Success Ratio(BSR) according to the characteristics of overseas projects

GGRHC4_2019_v20n3_122_t0002.png 이미지

Table 3. Descriptive statistics of international bidding results by region

GGRHC4_2019_v20n3_122_t0003.png 이미지

Table 4. Kruskal-Wallis tests of BSR by region

GGRHC4_2019_v20n3_122_t0004.png 이미지

Table 5. Descriptive statistics of international bidding results by work type

GGRHC4_2019_v20n3_122_t0005.png 이미지

Table 6. Kruskal-Wallis tests of BSR by work type

GGRHC4_2019_v20n3_122_t0006.png 이미지

Table 7. Descriptive statistics of international bidding results by project size

GGRHC4_2019_v20n3_122_t0007.png 이미지

Table 8. Kruskal-Wallis tests of BSR by project size

GGRHC4_2019_v20n3_122_t0008.png 이미지

Table 9. Descriptive statistics of international bidding results by project duration

GGRHC4_2019_v20n3_122_t0009.png 이미지

Table 10. Kruskal-Wallis tests of BSR by Project duration

GGRHC4_2019_v20n3_122_t0010.png 이미지

Table 11. Descriptive statistics of international bidding results by bidding type

GGRHC4_2019_v20n3_122_t0011.png 이미지

Table 12. Kruskal-Wallis tests of BSR by bidding type

GGRHC4_2019_v20n3_122_t0012.png 이미지

Table 13. Descriptive statistics of international bidding results by contract type

GGRHC4_2019_v20n3_122_t0013.png 이미지

Table 14. Descriptive statistics of international bidding results by client type

GGRHC4_2019_v20n3_122_t0014.png 이미지

Table 15. Kruskal-Wallis tests of BSR by client type

GGRHC4_2019_v20n3_122_t0015.png 이미지

Table 16. Descriptive statistics of international bidding results by period

GGRHC4_2019_v20n3_122_t0016.png 이미지

References

  1. Aje, I.O., Oladinrin, T.O., and Nwaole, A.N.C. (2016). "Factors Influencing Success Rate of Contractors in Competitive Bidding for Construction Works in South-East, Nigeria." Journal of Construction in Developing Countries, 21(1), pp. 19-34. https://doi.org/10.21315/jcdc2016.21.1.2
  2. Aznar, B., Pellicer, E., Davis, S., and Ballesteros-Perez, P. (2017). "Factors affecting contractor's bidding success for international infrastructure projects in Australia." Journal of Civil Engineering and Management, 23(7), pp. 880-889. https://doi.org/10.3846/13923730.2017.1341955
  3. Bu-Qammaz, A.S., Dikmen, I., and Birgonul, M.T. (2009). "Risk assessment of international construction projects using the analytic network process." Canadian Journal of Civil Engineering, 36(7), pp. 1170-1181. https://doi.org/10.1139/L09-061
  4. Chua, D.K.H., and Li, D. (2000). "Key factors in bid reasoning model." Journal of Construction Engineering and Management, 126(5), pp. 349-357. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:5(349)
  5. Drew, D.S., and Skitmore, M. (1997). "The effect of contract type and size on competitiveness in bidding." Construction Management and Economics, 15(5), pp. 469-89. https://doi.org/10.1080/014461997372836
  6. Dikmen, I., and Birgonul, M.T. (2004). "Neural network model to support international market entry decisions." Journal of Construction Engineering and Management, 130(1), pp. 59-66. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(59)
  7. Dikmen, I., and Birgonul, M.T. (2006). "An analytic hierarchy process based model for risk and opportunity assessment of international construction projects." Canadian Journal of Civil Engineering, 33(1), pp. 58-68. https://doi.org/10.1139/l05-087
  8. Dikmen, I., Birgonul, M.T., and Gur, A.K. (2007a). "A case-based decision support tool for bid mark-up estimation of international construction projects." Automation in Construction, 17(1), pp. 30-44. https://doi.org/10.1016/j.autcon.2007.02.009
  9. Dikmen, I., Birgonul, M.T., and Han, S.H. (2007b). "Using fuzzy risk assessment to rate cost overrun risk in international construction projects." International Journal of Project Management, 25(5), pp. 494-505. https://doi.org/10.1016/j.ijproman.2006.12.002
  10. Gunhan, S., and Arditi, D. (2005). "Factors Affecting International Construction." J. Constr. Eng. Manage., 131(3), pp. 273-282. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:3(273)
  11. Flanagan, R. Lu, W., Shen. L., and Jewell, C. (2007). "Competitiveness in Construction: a critical review of research." Construction Management and Economics, 25(9), pp. 989-1000. https://doi.org/10.1080/01446190701258039
  12. Han, S.H., and Diekmann, J.E. (2001). "Making a risk-based bid decision for overseas construction projects." Construction Management and Economics, 19(8), pp. 765-776. https://doi.org/10.1080/01446190110072860
  13. Han, S.H., Diekmann, J.E., and Ock, J.H. (2005). "Contractor's risk attitudes in the selection of international construction projects." Journal of Construction Engineering and Management, 131(3), pp. 283-292. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:3(283)
  14. Hwang, J.S., and Kim, Y.S. (2016). "A bid decision-making model in the initial bidding phase for overseas construction projects." KSCE Journal of Civil Engineering, 20(4), pp. 1189-1200. https://doi.org/10.1007/s12205-015-0760-y
  15. Jang, W., Lee, J.K., Lee, J., and Han, S.H. (2015). "Naive Bayesian Classifier for Selecting Good/Bad Projects during the Early Stage of International Construction Bidding Decisions." Mathematical Problems in Engineering, vol. 2015, Article ID 830781, 12 pages, 2015.
  16. Jaselskis, E.J., and Talukhaba, A. (1998). "Bidding considerations in developing countries." Journal of Construction Engineering and Management, 124(3), pp. 185-193. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:3(185)
  17. Kim, D.Y., Han, S.H., and Kim, H. (2008). "Discriminant analysis for predicting ranges of cost variance in international construction projects." Journal of Construction Engineering and Management, 134(6), pp. 398-410. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:6(398)
  18. Kim, J., and Kim Y. (2014). "An Analysis of Profitability Study of Overseas Construction Projects using Multiple-Regression." Korean Journal of Construction Engineering and Management, KICEM, 15(2) pp. 95-103.
  19. Ling, F.Y.Y. (2005). "Global factors affecting margin-size of construction projects." Journal of Construction Research, 6(1), pp. 91-106. https://doi.org/10.1142/S1609945105000274
  20. Lu, W.S. (2006). "A system for assessing and communicating contractors' competitiveness, thesis submitted to the Degree of Doctor of Philosophy in the Department of Building and Real Estate, the Hong Kong Polytechnic University, Hong Kong.
  21. Ofori, G. (2003). "Frameworks for analysing international construction." Construction Management and Economics, 21, pp. 379-391. https://doi.org/10.1080/0144619032000049746
  22. OO, B.L., Drew, D.S., and Runeson, G. (2010). "Competitor analysis in construction bidding." Construction Management and Economics, 28, pp. 1321-1329. https://doi.org/10.1080/01446193.2010.520721
  23. Polat, G., and Bingol, B.N. (2013). "A comparison of fuzzy logic and multiple regression analysis models in determining contingency in international construction projects." Construction Innovation, 13(4), pp. 445-462. https://doi.org/10.1108/CI-06-2012-0034
  24. Sohn, T.H. (2011). "A Study on Associations among Number of Bidders, Contract Award Rate and Profitability on International Construction." Journal of The Korean Society of Civil Engineers, 31(3), pp. 247-253.
  25. Sonmez, R., Ergin, A., and Birgonul, M.T. (2007). "Quantiative methodology for determination of cost contingency in international projects." Journal of Management in Engineering, 23(1), pp. 35-39. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:1(35)
  26. Yu, Y., Shin, B., Koo, B., and Han, S. (2018). "Using Logistic Regression for Determining the Facctors Affecting Bidding Success in World Bank's International Consulting Projects in Indonesia." Korean Journal of Construction Engineering and Management, KICEM, 19(1) pp. 80-89.