A Case Study of Construction Management for Pusan National University Children's Hospital

부산대학교 어린이병원 건립사업 CM 수행사례

  • 양진국 ((주)거성ENG건축사사무소 감리CM본부) ;
  • 이민현 ((주)거성ENG건축사사무소 감리CM본부)
  • Published : 2007.11.09

Abstract

The construction by the ministry of health and welfare support of the first special hospital for only children in busan and gyeong-nam is under building with YPNUH(Yangsan Pusan National University Hospital) for the best medical treatment town and is to improve the productivity and efficiency by eliminating unproductive and inefficient fact through the construction management, systemic and scientific management technique. So in this study we would like to suggest the generated effect to apply project management technique to all stage such as from pre-design phase, turn-key enterprise choice, construction, design VE(Value Engineering), PMIS (Project Management Information System) construction to maintenance phase and cost and schedule reduction effect through basic, execution design VE by using engineer of field.

보건복지부의 지원으로 건립하는 부산${\cdot}$경남 최초의 어린이전문병원 건립공사는 양산부산대학교병원과의 연계로 최고시설의 의료타운건립을 목표로 수행중이며 건설사업관리(CM)라는 체계적이고 과학적인 관리기법의 도입 및 적용을 통해 건설프로젝트의 비생산적이고 비효율적인 요소를 제거하여 생산성과 효율성을 향상시키고자 하는 것이다. 이에 본 연구에서는 어린이병원건립사업에 사업관리기법을 설계이전단계부터 턴키업체선정, 시공, 설계VE, PMIS구축, 유지관리단계의 사업 전(全)단계에 적용하여 발생한 효과와 분야별 기술자를 활용한 기본 및 실시설계VE를 통한 사업비 절감 및 공기단축 효과를 제시하고자 한다.

Keywords