An RFID and BIM based Simulator for Construction Material Logistics and Progress Management

RFID와 BIM을 활용한 건설 자재 물류 및 진도관리 시뮬레이터 개발

  • 윤수원 ((주)두올테크 건설기술연구소) ;
  • 진상윤 (성균관대학교 건축공학과)
  • Received : 2011.03.16
  • Accepted : 2011.03.25
  • Published : 2011.09.30

Abstract

There have been research and developments for effective and efficient logistics and progress management in a construction project. Among them, RFID+4D has been developed for the supply chain management of long-lead item materials such as steel component, precast concrete component and curtain wall by integrating RFID with 4D CAD. And the feasibility of RFID+4D has been verified and validated and the benefits in terms of time and cost were shown in several case studies. However, the previous development of RFID+4D has not been adapted widely because of additional modeling cost, non-real time data update, additional labor for data update, and so forth. Therefore, this research has proposed a framework and process for solving these problems. And the web based simulation system has been developed and verified based on the proposed framework. The proposed framework and process can improve the existing RFID+4D system in a construction project by saving its operation cost and utilizing project information more efficiently and effectively. Also it is expected that the proposed framework could be applied to a method transferring design RIM data to construction BIM data.

건설 프로젝트의 효과적인 물류 및 진도관리를 위하여 다양한 연구 및 시도가 이루어지고 있다. 이중 RFID+4D 기술은 철골, PC, 커튼월과 같은 공장 주문형 자재의 공급망 및 진도관리를 위해 개발된 기술로써 공기 및 비용 절감에 대한 효과가 있는 시스템으로 보고된 바 있다. 하지만 기존의 시스템은 그 효과에 비해 모델링 비용, 실시간 정보 반영의 난이, 시스템 운영을 위한 추가 인력 배치 등의 문제로 인해 시스템 확산이 미비한 상태에 있다. 따라서 본 연구에서는 이러한 기존 RFID+4D 프로세스의 문제를 해결하기 위한 체계 및 제안된 체계를 활용한 웹 기반의 실시간 4D 시뮬레이터를 개발하였다. 본 연구에서 개발된 체계 및 시스템은 기존 RFID+4D 프로세스 운영의 비용 및 정보 활용성을 향상시킴으로써 기술 확산에 기여할 것으로 기대되며 특히 최근 이슈화되고 있는 BIM 정보와의 연계를 통해 설계 단계에서 생성된 BIM을 시공 단계에서 활용하기 위한 방법으로 활용 가능할 것으로 판단된다.

Keywords

References

  1. 신봉수∙김창덕 (2004). "건설공사의 적시생산(Just-In-Time)을 위한 양중시스템 개발."한국건설관리학회 논문집, 제 5 권 제 6호, 한국건설관리학회, pp. 235-244.
  2. 안병주.김재준.김경래.김선규 (1999)." 고층 건물 공사 현장 레이아웃의 최적화에 관한 연구."대한건축학회 논문집(구조계), 제 15권 제12호, 대한건축학회, pp. 107-119.
  3. 오명진.황영삼 (2002)." IFC기반 건축현장 자재구매관리 모델개발 가능성에 관한 연구."대한건축학회 추계학술발표대회논문집, 제22권 제2호, 대한건축학회, pp887-890.
  4. 임형철.송성진(2004)." 현장 공정 커뮤니케이션을 통한 공장생산자재의 공급 및 생산관리 방안에 관한 연구."대한건축학회논문집(구조계), 제 20권 제4호, 대한건축학회, pp. 143-152.
  5. 윤수원(2008)." RFID 기반커튼월 공사 물류 및 진도 통합 관리 시스템."성균관대학교 박사학위 논문.
  6. Arbulu, J. R. and Tommelein, D. I. (2002)." Value Stream Analysis of Construction Supply Chains."Proceedings of IGLC-10, Gramado, Brazil.
  7. Chin, S. . Yoon, S. W. . Kim, Y. S..Ryu J..Choi, C. and Cho, C. Y. (2005)." Real time 4D CAD+RFID for Project Progress Management."Proceedings of construction Research Congress, San Diego, California, U. S. A. pp. 33-43.
  8. Chin, S..Yoon, S. W..Choi, C. and Cho, C. (2008)." RFID + 4D CAD for Progress Management of Structural Steel Works in High-Rise Buildings."Journal of Computing in Civil Engineering, 22(2), ASCE, pp. 74-89. https://doi.org/10.1061/(ASCE)0887-3801(2008)22:2(74)
  9. Esin E..Burcu, A..Bill, E. and Jeff, K. (2007)." Tracking Components and Maintenance History within a Facility Utilizing Radio Frequency Identification Technology."Journal of Computing in Civil Engineering, 21(1). ASECE, pp. 11-20. https://doi.org/10.1061/(ASCE)0887-3801(2007)21:1(11)
  10. Fiho, A. and Menezes, E. (2002). "Development of an Operational Parameter Measuring System." Proceedings of IGLS-10, Gramado, Brazil.
  11. Jaselskis, E. J..Anderson, M. R..Jahren, C. T.. Rodriguez, Y. and Njos, S. (1995)." Radio-Frequency Identification Application in construction Industry." Journal of Construction Engineering and Management, 121(2), ASCE, pp. 189-196. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:2(189)
  12. Jaselskis, E. J. and EI-Misalami, T. (2003)." Implementing Radio Frequency Identification in Construction Process."Journal of Construction Engineering and Management, 129(6), ASCE, pp. 680-688. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:6(680)
  13. Naven, R. and Goldschmidt, E. (2002). "Monitoring Labor Inputs: Automated-Data-Collection Model and Enabling Technologies.", Automation in Construction, 12(2), pp. 185-199.
  14. Pheng, S. P. and Chuan, C. J. (2001). "Just-In-Time Management of Precast Conctrete Components." Journal of Construction Engineering and Management, 127(6), ASCE, pp. 494-501. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(494)
  15. Song, J..Haas, C. T. Caldas, C..Ergen, E. and Akinci, B.(2005). "Automating the task of tracking the delivery and receipt of fabricated pipe spool in industry projects."Automation in construction, 15(2),pp. 166-177
  16. Vela systems (2007). http://www.cif.org/noms/2008/09_ - _Real-Time_BIM-RFID_Project_Management.pdf (2011. 02. 15)

Cited by

  1. Development Strategies and Feasibility Evaluation of Maintenance Operation System for Railway Bridge Based on Ubiquitous-BIM Technology vol.15, pp.5, 2012, https://doi.org/10.7782/JKSR.2012.15.5.459
  2. A Context-Driven Model for the Flat Roofs Construction Process through Sensing Systems, Internet-of-Things and Last Planner System vol.17, pp.7, 2017, https://doi.org/10.3390/s17071691
  3. Prefabricated construction enabled by the Internet-of-Things vol.76, 2017, https://doi.org/10.1016/j.autcon.2017.01.006
  4. A Development of Framework for Selecting Labor Attendance Management System Considering Condition of Construction Site vol.16, pp.4, 2015, https://doi.org/10.6106/KJCEM.2015.16.4.060